Note: Crude Oil and Natural Gas Pipelines in North America: A Barrel Full
Updates
February 3, 2020: Enbridge Line 3 replacement -- last hurdle cleared?
October 19, 2019: the Bridger Expansion -- huge;
May 1, 2018: Gray Oak Pipeline -- the Permian to Corpus Christi. One million bopd.
November 20, 2017: Nebraska regulators vote "no" with a 3-2 "yes" vote to approve the Keystone XL.
March 27, 2017: DAPL pipeline oil under the lake.
November 28, 2016; huge, huge, huge story. Spectra Energy to expand pipeline capacity from Guernsey, WY, to Patoka, IL.
November 25, 2016: US Army Corps of Engineers closes the protest camp north of the Cannonball River. ND state attorney rules in favor of DAPL; Trump sells shares of ETP.
September 5, 2016: more reporters than protesters, but over at CNN, the report is that it's getting more tense in North Dakota over the Dakota Access Pipeline; Native Americans ask for "emergency" injunction against any more construction. Link to CNN; the link will eventually break.
September 2, 2016: Enbridge puts the Sandpiper Pipeline project on hold.
August 29, 2016: Dakota Access Pipeline keystoned by the Lakota in Dakota.
August 5, 2016: Sandpiper in doubt. MRO pulls out; Enbridge re-evaluates. Emphasis now on Dakota Access.
May 27, 2016: Dakota Access Pipeline keystoned in Iowa, as predicted.
April 19, 2016: when Iowa approved the Dakota Access pipeline permit, it also approved use of eminent domain. As expected, a lawsuit has been filed to prevent that use of eminent domain (as of April 12, 2016).
April 11, 2016: Iowa formally issues Dakota Access pipeline permit -- Dickinson Press.
January 20, 2016: North Dakota approves Dakota Access Pipeline. Only Iowa yet to approve, which the company expects "next month." US Army Corps of Engineers also have to approve portion that goes under Missouri River.
December 9, 2015: update on TransCanada's Upland Pipeline project and ETP's Dakota Access Pipeline project staging areas west of Williston.
November 30, 2015: South Dakota approves its segment of the ETP Dakota Access Pipeline, but one dissenter suggests it will end up in court.
October 19, 2015: RBN begins series on Enbridge Line 9 reversal and what it means for the Bakken.
October 10, 2015: Two stories from Argus Media on Enbridge Line 9: good news in the big scheme of things. Some ankle biters by NIMBYs.
August 31, 2015: Van Hook Gathering System, bought by Ares in 2015, built by WPX.
August 10, 2015: KMI announces crude oil starts to move on Double H.
January 17, 2015: one last line of defense to stop Enbridge Line 61 expansion.
January 14, 2015: open comment period on the northern portion of the BakkenLink, from Tioga/Hess to Watford City.
June 25, 2014: North Dakota PSC approves the Enbridge Sandpiper pipeline. Minnesota and Wisconsin still need to act, I believe.
October 31, 2013: mostly fluff, but The Motley Fool briefly updates the major pipelines of interest.
October 19, 2019: the Bridger Expansion -- huge;
May 1, 2018: Gray Oak Pipeline -- the Permian to Corpus Christi. One million bopd.
November 20, 2017: Nebraska regulators vote "no" with a 3-2 "yes" vote to approve the Keystone XL.
March 27, 2017: DAPL pipeline oil under the lake.
November 28, 2016; huge, huge, huge story. Spectra Energy to expand pipeline capacity from Guernsey, WY, to Patoka, IL.
November 25, 2016: US Army Corps of Engineers closes the protest camp north of the Cannonball River. ND state attorney rules in favor of DAPL; Trump sells shares of ETP.
September 5, 2016: more reporters than protesters, but over at CNN, the report is that it's getting more tense in North Dakota over the Dakota Access Pipeline; Native Americans ask for "emergency" injunction against any more construction. Link to CNN; the link will eventually break.
September 2, 2016: Enbridge puts the Sandpiper Pipeline project on hold.
August 29, 2016: Dakota Access Pipeline keystoned by the Lakota in Dakota.
August 5, 2016: Sandpiper in doubt. MRO pulls out; Enbridge re-evaluates. Emphasis now on Dakota Access.
May 27, 2016: Dakota Access Pipeline keystoned in Iowa, as predicted.
April 19, 2016: when Iowa approved the Dakota Access pipeline permit, it also approved use of eminent domain. As expected, a lawsuit has been filed to prevent that use of eminent domain (as of April 12, 2016).
April 11, 2016: Iowa formally issues Dakota Access pipeline permit -- Dickinson Press.
January 20, 2016: North Dakota approves Dakota Access Pipeline. Only Iowa yet to approve, which the company expects "next month." US Army Corps of Engineers also have to approve portion that goes under Missouri River.
December 9, 2015: update on TransCanada's Upland Pipeline project and ETP's Dakota Access Pipeline project staging areas west of Williston.
November 30, 2015: South Dakota approves its segment of the ETP Dakota Access Pipeline, but one dissenter suggests it will end up in court.
October 19, 2015: RBN begins series on Enbridge Line 9 reversal and what it means for the Bakken.
October 10, 2015: Two stories from Argus Media on Enbridge Line 9: good news in the big scheme of things. Some ankle biters by NIMBYs.
August 31, 2015: Van Hook Gathering System, bought by Ares in 2015, built by WPX.
August 10, 2015: KMI announces crude oil starts to move on Double H.
January 17, 2015: one last line of defense to stop Enbridge Line 61 expansion.
January 14, 2015: open comment period on the northern portion of the BakkenLink, from Tioga/Hess to Watford City.
June 25, 2014: North Dakota PSC approves the Enbridge Sandpiper pipeline. Minnesota and Wisconsin still need to act, I believe.
October 31, 2013: mostly fluff, but The Motley Fool briefly updates the major pipelines of interest.
By 2014 the United States of America will overtake Russia in liquids production, which is estimated to hit 11 million barrels per day versus 10.86 million bpd for Russia. But the bigger question is how will America move 40 billion barrels a year?
Well up north Enbridge Energy Partners is lending a helping hand with several projects coming up. The Bakken is seeing booming production, and someone has to be able to transport all that oil to the refineries.
Enbridge Energy Partners is building a 225,000 bpd pipeline from the Bakken to Clearbrook, Minnesota. From Clearbrook, Enbridge Energy Partners is building a 375,000 bpd pipeline to Superior, Wisconsin. Both of these projects will be done around 2016 and will allow oil from the Bakken to reach refiners out east.
In order to make sure as much oil as possible is hooked up to Enbridge Energy Partner's pipelines, it is building a 100,000 bpd regional access system which will come online in the third quarter of 2013.August 25, 2013: Wall Street Cheat Sheet provides background to three pipelines that are as "environmentally dangerous" as the Keystone XL according to activist environmentalists (some of them noted below): a) the Bluegrass Pipeline; b) the TransCanada's Energy East Pipeline (entirely within Canada, skirting Maine); and, c) Enbridge's Eastern Gulf Crude Oil Access Pipeline.
- Bluegrass Pipeline: across Kentucky; 500 miles; natural gas; from western border of Pennsylvania to Arkansas, where it will connect with existing line to the Gulf
- Energy East Pipeline: most expensive TransCanada project ever; $12 billion; converting 1800 miles to natural gas pipeline to handle crude oil
- Eastern Gulf Crude Oil Access Pipeline: 770 miles, crude oil, Illinois (Patoka/Johnsonville) to Louisiana
My List
Liberty Pipeline
First mention here (link here):
- Liberty Pipeline, a joint venture between two companies:
- Phillips 66
- Bridger Pipeline
- The project:
- origin: the Bakken; southwest corner of North Dakota
- via: Guernsey, WY
- terminal: Cushing, Oklahoma
- route not yet clear
- proposed capacity: 200,000 bbls
- cost: $1.6 billion
- in-service date: as early as 1Q21 (hope springs eternal)
Two legs (link here):
- Dakota Access Pipeline (see below)
- Energy Transfer Crude Oil Pipeline
Dakota Access Pipeline
North Portion: under the river/lake, Beaver Lodge to Johnson Corner (Watford City)
South Portion: Johnson Corner to Fryburg, about 35 miles west of Dickinson, ND
Update here.
Data points:
TransCanada Upland: Williston-to-Canada
Initial post: February 14, 2015
Rigzone: April 27, 2015
DAPL
Energy Transfer Partners (ETP): Bakken-To-Patoka, IL
Dakota Access Pipeline
Posts:
Data points:
Enbridge BakkenLink: Beaver Lodge (Tioga) to Fryburg (southwestern ND)- November 9, 2016: map of the area under contention, Standing Rock Reservation
- August 5, 2016: now part of the Bakken Pipeline System
- May 13, 2015: pipe being staged
Data points:
- Completed:
- Length: 1,168 miles; 30-inch diameter
- Origin:
- Terminal:
- Capacity: 450,000 bopd; max, 570,000 bopd
- Cost: $3.7 billion project per ETP; $1 million/mile = $1.1 billion
- Comment: ETP hopes to have this completed by late 2016; update -- Iowa keystoned the project in early 2016;
North Portion: under the river/lake, Beaver Lodge to Johnson Corner (Watford City)
South Portion: Johnson Corner to Fryburg, about 35 miles west of Dickinson, ND
Update here.
Data points:
- Completed:
- Length:
- Origin: Beaver Lodge (Tioga)
- Terminal: Fryburg, ND, via Johnson Corner (Watford City)
- Capacity:
- Cost:
- Comment: northern portion will set depth/distance record for horizontal/direction pipeline
TransCanada Upland: Williston-to-Canada
Initial post: February 14, 2015
Rigzone: April 27, 2015
Data points:
- Status: permit request to President Obama, April, 2015
- Completed:
- Length: 240 miles
- Origin: Williston, North Dakota
- Terminal: Manitoba/Saskatchewan border to meet the proposed TransCanada Energy East pipeline
- Capacity: 220,000 bopd (remember the Keystone XL was going to have about 850,000 bopd capacity and very little of that would carry Bakken crude oil)
- Cost: $500 million
DAPL
Energy Transfer Partners (ETP): Bakken-To-Patoka, IL
Dakota Access Pipeline
Announced: June 26, 2014 (story here)
Anticipated completion: 4Q16
Note: "replaces" Koch Bros "Dakota Express"
Updates: South Dakota approves its segment, November 30, 2015; North Dakota approves, January 20, 2016; Iowa last state, expected to approve "next month (February, 2016)"; US Army Corps of Engineers need to approve that portion under the Missouri River
Data points:
- "Go-By Name": Dakota Access Pipeline
- Completed: March 27, 2017: DAPL pipeline oil under the lake.
- Length: 1,150 miles
- Origin: North Dakota
- Terminal: Patoka, IL
- Capacity: 320,000 bopd (remember the Keystone XL was going to have about 850,000 bopd capacity and very little of that would carry Bakken crude oil); in January 20, 2016, update, the pipeline was said to be able to carry 600,000 bopd
- Cost: $3.8 billion;
EPD: Bakken-To-Cushing
Data points:
- Announced: June 24, 2014 (story here)
- Anticipated completion: 4Q16
- Completed:
- Length: 1,200
- Origin: Stanley, ND
- Terminal: Cushing, OK
- Capacity: 30-inch diameter; 340,000 bopd (remember the Keystone XL was going to have about 850,000 bopd capacity and very little of that would carry Bakken crude oil)
- Cost: [my estimate: 1200 miles x $400K/mile = 480,000K = $480 million]
- Impact: huge; if I recall correctly, OKE proposed something similar but canceled plans
Belle Fourche Pipeline #2, Billings County To Dickinson, North Dakota
Data points:
- Announced: June 18 2014 (story here); to parallel an existing Belle Fourche pipeline
- Anticipated completion:
- Completed:
- Length: 20 miles
- Origin: southeast Billings County
- Terminal: MDU/Calument refinery / CBR west of Dickinson
- Capacity: 100,000 bopd (about 15% of the Bakken output)
- Cost: $8 million
- Impact: huge; another 100,000 bopd for the refinery and CBR; complements the Killdeer-Dickinson line; parallels an existing pipeline
Data points:
- Unofficial "Go-By" Name:
- Announced: 2013
- Originator: TransCanada
- Pipeline: crude oil
- Specs:
- Origin: most likely, Hardisty, Alberta, Canada
- Terminus: Montreal, Quebec City and Saint John, N.B.
- Length:
- Capacity: 850,000 bopd (original post); January 7, 2014, according to RBN Energy: 1.1 million bopd
- Comments: alternative to Keystone XL if disapproved; could be in addition to Keystone XL if the latter is approved; Energy East also would displace foreign crude. About half of the crude oil that would flow through the pipeline would be destined for export markets, with the remainder processed at domestic refineries. Refineries in the northeastern U.S., Europe and India’s west coast are possible customers for Energy East’s crude.
- Concerns:
- Status: $11 billion project application formally filed October 30, 2014; link here to WSJ;
Enbridge
Line 9A Reversal
Line 9A Reversal
Line 5 Expansion
Line 79
Western Canada to Montreal, Quebec
Update: project completed, October 19, 2015.
Update: apparently regulators have given Enbridge approval to open its Line 9 crude pipeline. October, 2, 2015. Story here.
Update: apparently regulators have given Enbridge approval to open its Line 9 crude pipeline. October, 2, 2015. Story here.
- Line 9A, reversal, from Sarnia, Ontario, (northeast of Detroit) to North Westover, Ontario: about 120 miles; should be complete by early-2014; 200,000 bopd
- Line 9B: reversal already approved;
- Line 5, expansion, Superior, MN, to Sarnia, Ontario: should be completed early this year
- Line 79, new, between Stockbridge and Romulus, MI; 50-mile stretch west of Detroit; enters service April, 2013; new pipe and existing leased pipe
- Line 6B (Lakehead), replacement work, between Griffith, IN, and Stockbridge, MI: 200 miles west of Stockbridge; done by end of 2013; Stockbridge, MI, to St Clair River in Marysville, MI, 350 miles running from south, up to Stockbridge, MI; done by early 2014; [seems like two separate lines, one running west to east (Bakken); one running south to North (Cushing)]; Line 6B Phase 2 replacement; replace 75 miles of old pipe; full pipeline will have replaced (sic) once Phase 2 is complete, increasing capacity to 500K bopd from 240K bopd.
- Line 62, expansion, Spearhead North Pipeline, from Flanagan, IL, to terminal at Griffith, IN: to 235K bopd from 130K by adding horsepower. (Flanagan, IL: southwest of Chicago; out in the middle of nowhere)
Enbridge
Sandpiper
Enbridge Light Oil Market Access Program
Western Canada to Montreal, Quebec
Update, September 2, 2016: formally on hold.
Update, August 5, 2016: looks to be in trouble; MRO pulls out; Enbridge to re-evaluate need;
Update: Minnesota activists are attempting to keystone the Sandpiper; could be successful; both parties want Minnesota Supreme Court to rule, Octobber 19, 2015.
Comment: this is a key line taking Bakken to Superior, MN, where it would hook up with Line 5, to get crude oil back into Canada. (Map here; though regional media source; link will probably break)
Unofficial "Go-By" Name:
Enbridge Light Oil Market Access Program
Western Canada to Montreal, Quebec
Update, September 2, 2016: formally on hold.
Update, August 5, 2016: looks to be in trouble; MRO pulls out; Enbridge to re-evaluate need;
Update: Minnesota activists are attempting to keystone the Sandpiper; could be successful; both parties want Minnesota Supreme Court to rule, Octobber 19, 2015.
Comment: this is a key line taking Bakken to Superior, MN, where it would hook up with Line 5, to get crude oil back into Canada. (Map here; though regional media source; link will probably break)
Unofficial "Go-By" Name:
Announced:
Expected completion: 2016
Expected completion: 2016
Originator: Enbridge
Pipeline: crude oil
Specs: $2.6 billioin
Origin: Beaver Lodge Terminal, Tioga, North Dakota
Terminus: Superior, WI, Terminal via Clearbrook, MN
Length: 600 miles
Capacity: 225,000 bopd (approx 20% of Bakken output)
Comments:
Concerns: northern Minnesota activists in Clearbridge area
Status: initial application was not approved by FERC in March, 2013; Enbridge says project remains on schedule. Update, October 29, 2013: The Bismarck Tribune reports that the Minnesota PUC will take a year to listen to local farmers who oppose the pipeline. Update: June 25, 2014: North Dakota PSC approves the pipeline. Update: June 5, 2015: Minnesota approves certificate of need for the pipeline; lengthy review for route still envisioned. Update: October, 2015: court nullifies PUC certificate of need; both parties now want Minnesota Supreme Court to intervene;
Enbridge
SAX
Southern Access Extension Pipeline
Will connect ENB's huge Lakehead system running from Western Canada to Flanagan, IL, with EGCAP (Energy Transfer) in Patoka, IL
Southern Access Extension Pipeline
Will connect ENB's huge Lakehead system running from Western Canada to Flanagan, IL, with EGCAP (Energy Transfer) in Patoka, IL
A short pipeline between Flanagan, IL, and Patoka, IL (connects pipeline from the Gulf Coast to a pipeline from western Canada)
Enbridge
Flanagan South
Comment: will get heavy oil to Gulf Coast; Enbridge: "will provide the additional
capacity needed to bring increased North American crude oil production
to refinery hubs in the U.S. Gulf Coast"; Chicago area to Cushing where it will hook-up with reverse Seaway to get oil to Gulf coast.
Unofficial "Go-By" Name:
Announced:
Originator: Enbridge
Pipeline: heavy crude oil
Specs: 36-inch diameter
Origin: Flanagan, IL
Terminus: Cushing, OK
Length: 600 miles
Capacity: 600,000 bopd, initially
Comments: will parallel Enbridge’s existing
Spearhead crude oil pipeline right-of-way; does not go through Nebraska
Concerns:
Enbridge
Line 61 Upgrade Project
Two Phases
Line 61 Upgrade Project
Two Phases
Phase 1: increasing the
capacity on Line 61 (referred to as Southern Access Project during its
construction in 2007) between Enbridge’s Superior, WI, Terminal and
Flanagan Terminal near Pontiac, IL. The Line 61 Project expands the
capacity of the 42-inch pipeline from 400,000 bpd to 560,000 bpd.
The construction of Phase 1 Project was completed in the
summer of 2014, allowing the 560,000 bpd capacity to begin flowing
September 2014.
Phase 2: Enbridge is expanding the average annual capacity of Line 61 from
560,000 barrels per day (bpd) to 1.2 million bpd. Enbridge is expanding in phases the average
annual capacity of our Line 61 Pipeline to an ultimate 1.2 million
barrel per day (bpd) design capacity. Line 61 is a 42-inch-diameter
crude oil pipeline that spans from Enbridge’s terminal in Superior,
Wisconsin, to our Flanagan Terminal near Pontiac, Illinois.
- Phase 2 will increase Line 61 to its full 1.2 bpd design capacity
To increase Line 61’s capacity to its full 1.2 million bpd design
capacity, Enbridge is constructing or modifying pump stations located in Wisconsin and Illinois.
All work will be performed on property that is owned or acquired in
fee by Enbridge. The Project does not require pipeline construction.
Construction for Phase 2 began in spring 2014 and, subject to permit
and regulatory approvals, the pipeline will be operating at a capacity
of 1.2 million bpd in 2015.
This is simply an upgrade in pumping stations.
Harold Hamm/CLR/Hiland
Unofficial "Go-By" Name: "Double H"
Announced: April, 2013
Owner: both Hiland and Double H acquired by Kinder Morgan in 2015
Originator: Harold Hamm, Hiland Partners; Continental Resources
Originator: Harold Hamm, Hiland Partners; Continental Resources
Pipeline: crude oil
Specs: 12"
Origin: Dore, Fairview, ND
Terminus: Guernsey, WY, via Baker, MT
Length: 462 miles
Capacity: 50 K with expansion to 100K
Comments: depends on Pony Express Pipeline
Concerns: close relationship between CLR and Hiland -- WSJ; August 10, 2015: KMI announces crude oil starts to move on Double H.
Status: see this post.Comments: depends on Pony Express Pipeline
Concerns: close relationship between CLR and Hiland -- WSJ; August 10, 2015: KMI announces crude oil starts to move on Double H.
Specta Energy Expansion -- Guernsey, WY, to Patoka, IL
Announced November 28, 2016
Link here. In light of the DAPL issue, this makes perfect sense.
New Town Expansion
Hiland
Announced September 18, 2015
Purpose: conversion of an existing gathering line to a transmission line
Owner: Kinder Morgan
No new pipeline; some new above-ground structures
Cost: $15 million
Tallgrass
Pony Express Pipeline
CNP-XTO
Unofficial "Go-By" Name:
Announced: ? -- in conjunction with the "Double H" pipeline (April, 2013)
Originator: Tallgrass Pony Express Pipeline, LLC
Pipeline: natural gas pipeline being retrofitted to carry crude oil; 260-mile new pipeline (KS to OK)
Specs: 24"
Origin: Guernsey, Wyoming
Terminus: Cushing, Oklahoma
Length:
Capacity: 230K to 320K
Comments: will transport Bakken oil to Cushing, Oklahoma; announced about same time as "Double H": at time of announcement, approval of the Keystone XL permit was still questionable;
CNP-XTO
Unofficial "Go-By" Name:
Announced: April 9, 2013
Originator: CNP, XTO
Pipeline:
Specs:
Origin: in-state
Terminus: in-state
Length:
Capacity: 19.5K
Comments:
an in-state crude oil gathering pipeline system
Concerns:
Status:
Status: open announced January 30, 2014; if successful; construction, 2016; on-line, 2017
*******************************************
Enbridge's Alberta Clipper
AKA: Line 67
*******************************************
Status:
Unofficial "Go-By" Name:
Announced: May 30, 2013; open season announced January 30, 2014;
Cost: $700 million
Cost: $700 million
Originator: MDU subsidiary MBI
Pipeline: natural gas
Specs:
Origin: in-state (western North Dakota, Bakken)
Terminus: northwest Minnesota
Length: 325 miles (in open season announcement, said to 375 miles)
Capacity: 400 million cfd; could expand to 500 million cfd (could heat 1.3 million homes annually)
Comments: energy for Minnesota; feedstock for new fertilizer plants in North Dakota (Jamestown, GR)
Concerns:Status: open announced January 30, 2014; if successful; construction, 2016; on-line, 2017
*******************************************
Enbridge's Alberta Clipper
AKA: Line 67
February 13, 2017: update. We're talking a 3-mile section of pipeline. For oil that is already crossing the border.
January 25, 2015: update.
November 13, 2014: it looks like Enbridge is playing "chicken" with US State Department.
August 25, 2014: did the US State Department approve Enbridge 67 "expansion"?
Enbridge Clipper: 800,000 bopd; Hardisty, Alberta (Canada) to Wisconsin (US). Received US permit in 2009; everything green-lighted; on February 14, 2014, it was announced that the US State Department wants a "do-over" on the environmental impact study.
June 13, 2014: update. See Flanagan South above.
Van Hook Gathering System, bought by Ares in 2015, built by WPX.
The Natural Gas Canadian/US Alliance Pipeline
January 25, 2015: update.
November 13, 2014: it looks like Enbridge is playing "chicken" with US State Department.
August 25, 2014: did the US State Department approve Enbridge 67 "expansion"?
Enbridge Clipper: 800,000 bopd; Hardisty, Alberta (Canada) to Wisconsin (US). Received US permit in 2009; everything green-lighted; on February 14, 2014, it was announced that the US State Department wants a "do-over" on the environmental impact study.
June 13, 2014: update. See Flanagan South above.
******************************************
OTHERS
Van Hook Gathering System, bought by Ares in 2015, built by WPX.
The Natural Gas Canadian/US Alliance Pipeline
- Completed, September 1, 2013; won't go into service until Hess Tioga gas processing plant enlarged
Tesoro's Bakken Area Storage Hub (BASH), expansion, announced February 4, 2014.
COMPLETED
Killdeer - Highway 22 - Dickinson, North Dakota
Bakken Oil Express
COMPLETED
Killdeer - Highway 22 - Dickinson, North Dakota
Bakken Oil Express
COMPLETED
Announced: December 28, 2013
Anticipated completion: early 2014
Completed: July 1, 2014 (story here)
Completed: July 1, 2014 (story here)
Length: 38 miles
Origin: Killdeer, North Dakota (two miles west of Killdeer)
Terminal: Dickinson, North Dakota (four miles west of Dickinson)
Capacity: 165,000 bopd (about 15% of the Bakken output)
Cost: $14 million
Impact: huge; essentially connects the southern one-half of the entire Bakken, from Williston south to Dickinson
ONEOK
Bakken NGL Pipeline
Completion announced April 10, 2013
Unfractionated NGL from the Bakken to the Overland Pass Pipeline; 525 miles, $500 million
Overland Pass Pipeline: 760 miles; southern Wyoming to Conway, KS
Began flowing: January 22, 2014
Cushing to Gulf coast: completed, December, 2013
Filling pipeline, late December
To start flowing January 22, 2014
Kinder Morgan
Koch
Dakota Express
Keystone XL 2.0
SOUTH
Cushing to Gulf coast: completed, December, 2013
Filling pipeline, late December
To start flowing January 22, 2014
******************************************
CANCELED
TransCanada
ORIGINAL
Dead. Killed by President Obama.
Data points:
Data points:
- Unofficial "Go-By" Name:
- Announced: 2008
- Originator: TransCanada
- Pipeline: crude oil
- Specs:
- Origin: Hardisty, Alberta, Canada
- Terminus: Steele City, Nebraska
- Length:
- Capacity:
- Comments:
- Concerns: political
- Status: in purgatory. In May, 2013, the government said don't expect decision until March, 2014;
- April 18, 2013: US Dept of State hearings in Grand Island, NE; locals and activists from out-of-state have converged; if approved, some locals and activists have promised significant civil disobedience.
Keystone XL 2.0
NORTH
Dead. Killed by President Obama.
Kinder Morgan
Permian to California
Koch
Dakota Express
Killed: January 22, 2014, announcement
Announced: June, 2013
Announced: June, 2013
Anticipated operational date: 2016
Capacity: 250,000 bopd
Terminals: western North Dakota (Bakken) to Patoka, IL, hub