Perhaps readers know better what is going on with these projects or can direct me to a better link. This is the best I could find overnight.

From Stratas Advisors, dated almost two years ago: largest-yet refinery project announced for North Dakota. Data points, again, this is almost two years old:
  • the state now has five refinery projects that may come online with the next ten (10) years
    • the five would add a combined processing capacity of about 155 Mbbl/d
  • Davis Refinery, near Belfield, Meridian Energy, begins first round of permit applications (this project has been discussed several times on the blog since then; it continues to move through the permitting process)
    • update, June 13, 2018: air quality permit approved
    • would be the largest new refinery int he state, and second largest refinery in ND overall
    • first phase: 27,500 bopd capacity; online in 2017 (did not happen)
    • second phase: permits to be filed when phase one is placed into service; will expand capacity to 55,000 bopd
    • goal: fully operational by 2019
  • Trenton, ND
    • Dakota Oil Processing
    • 20 Mbbl/day refinery
    • was to have been brought on line by end of 2016
  • Thunder Butte
    • Thunder Butte Petroleum Services
    • Makota, ND
  • Berthold, ND
    • Quantum Energy, Inc
    • 40 Mbbl/d
  • Stanley, ND
    • Quantum Energy, Inc
    • no further data

Thursday, December 12, 2013

New Refinery Proposed For North Dakota; West Of Devils Lake; $225 Million Project

The Bismarck Tribune is reporting:
Plans for an oil refinery in Devils Lake are exciting, but residents want information about the environmental consequences, especially in light of the lake's world-class fishery, Mayor Dick Johnson says.
American Energy Holdings, a Michigan-based company, announced plans to build a 20,000-barrel refinery on the west side of Devils Lake using crude from the Bakken oil patch.
Spokesman Mark Carlson said Wednesday the company is “ready to go” with the state’s first refinery east of the Missouri River to produce diesel, aviation fuel for the state’s two Air Force bases and naphtha, a hydrocarbon mixture from oil.
The $250 million plant will be called Bison Oil LLC and will depend on between 100 and 200 tanker truck loads daily out of the Bakken until it can get a pipeline in place, Carlson said.
A refinery project being considered for the reservation with the same capacity is conservatively estimated to cost about $450 million, $200 million more than the proposed Devils Lake project.

The MDU-Calumet refinery west of Dickinson is expected to be on-line sometime in 2014.

A third refinery, that one near Trenton, ND, is still in the planning stages. I haven't heard much about this refinery in a long, long time, and I think it was the first of the three that I had heard about when the boom first began in North Dakota (the three being the Trenton diesel refinery; the Dickinson/MDU-Calumet refinery; and the reservation refinery).

Friday, November 15, 2013

Did This Article Forget About The Dickinson Calumet-MDU Diesel Topping Plant ...

... or is the diesel topping plant not considered a refinery. According to MDU's 3Q13 earnings press release, the Calument-MDU diesel topping plant construction is on schedule.

In this article, this plant is not mentioned. The Minot Daily News is reporting:
A crew with heavy equipment began moving dirt this past weekend near Makoti for the construction of the transload facility, the first part of the Three Affiliated Tribes' clean fuels refinery project.
Glenda Baker Embry, public relations officer for the tribes, who visited the site Tuesday, said nine employees with Parks Construction, a Minneapolis firm, began the grading work at the site 2 1/2 miles west of Makoti on Saturday.
The construction of the transload facility is the first part of the tribal refinery project.
Costs for the refinery are conservatively estimated at $450 million, according to the article.

Later, in the article;
The refinery is conservatively estimated and projected to cost $450 million, according to tribal officials at the ground-breaking event.
The plans are for the refinery to refine Bakken Formation crude oil into diesel fuel, propane and naphtha products at the site in southwest Ward County, where the Three Affiliated Tribes own 469 acres of land. A portion of the land is specifically for the refinery. Some of the land will be used for feed for the tribes' bison.
The refinery will be one of the first refineries built in the United States in many years. The last refinery built in the U.S. was built in Garyville, La., and began operating in 1976.
The state has one refinery, the Tesoro Corp., in Mandan. Two other refinery projects have been proposed in North Dakota.
The two projects I am aware of:
  • Calumet-MDU, southwest Dickinson (noted at the beginning of this post
  • a diesel topping plant at Trenton

Wednesday, October 10, 2012

New Refinery in North Dakota? File Under: Why There's No Growth in the US -- A Decade To Get a Permit

Okay, maybe nine years. Whatever.

Link to Bismarck Tribune here
The Three Affiliated Tribes announced Wednesday that it has been given permit approval to take control of a piece of reservation land to build an oil refinery.

U.S. Secretary of the Interior Ken Salazar joined with tribal leaders at tribal headquarters to announce the permit approval, which brings a refinery one step closer to reality.
Nine years ago the tribe had requested that the Bureau of Indian Affairs, a part of the Department of the Interior, accept the acreage into a trust. The trust will allow the Interior department to own the land while allowing the tribe to control and manage it.
The tribe has wanted to use a 469-acre piece of land near Makoti to build the refinery and produce feed for the tribe’s buffalo herd. Plans call for the refinery to be built on a 190-acre portion of the land. The other land will be used for the buffalo.
The permitting process, which was nearly a decade in the making, opens the door for the construction of a new refinery in more than 30 years.
SecInterior Ken Salazar sounded jubilant in the news story; he should have been dismayed that it took nine years to get a permit.

Data points:
  • MHA Nation Clean Fuels Refinery
  • $400 million refinery
  • capacity of 13,000 bbls/day
  • Bakken oil --> diesel, gasoline, propane (I still don't see the "clean fuels" aspect of this, yet)
  • refinery site: along US Highway 23, on the edge of the Fort Berthold Indian Reservation
  • 800 to 1,000 jobs during construction phase
  • about 140 permanent jobs
  • nine years to get the permit

Friday, June 1, 2012

Update on Refinery Proposed for the Reservation

Link to Minot Daily Press here.

Data points:
  • Three Affiliated Tribes project; to be located near Makoti, southwest Ward County
  • Corval Group, St Paul, MN: business plan and finances; has an office in Beulah, ND
  • ASRC Energy Services, Alaska: expertise in engineering and operations;  
  • 15,000 bopd --> diesel, propane, and naphtha products
  • naphtha is a pipeline diluent for Canadian oil sands oil
  • estimated: $370 million
Two interesting quotes from the linked article:
ASRC Energy Services, based in Anchorage, Alaska, is a subsidiary of Arctic Slope Regional Corp., a private, for-profit Alaska Native owned corporation representing the interests of 11,000 Inupiant Eskimos, and considered one of the most successful corporations in Alaska. Mayer said ASRC, the parent company of ASRC Energy Services, has two refineries in Alaska one at North Pole and the other at Valdez. Both are located along the Trans-Alaska Pipeline. Mayer said the refinery at Valdez, built in the early 1990s, was the last refinery built in the U.S.
And,
The Three Affiliated Tribes' refinery will be the first refinery built in the contiguous United States in many years. The last one was built in Garyville, La., and began operating in 1976.
Unless something has changed, the 20,000 bopd refinery near Trenton, ND, was farthest along in the process; MDU is also planning to open a 20,000 bopd refinery near Dickinson, ND; it will be interesting to see which of the three is "first.

COMMENTARY -- READ AT OWN RISK

And for folks who wonder why I harp on the Feds slow-rolling the industry and why I do not look upon the EPA as "in touch with reality" -- not my words, those of the API:
Since early 2000, the Three Affiliated Tribes have been working on the refinery project, a project initiated by Tex Hall, tribal chairman, and approved by the tribal business council. The initial feed study was conducted in 2002-2003. However, it has taken a number of years for the tribes to obtain the environmental clearances.

In August 2011, the Environmental Protection Agency issued the final permit for the refinery, the National Pollutant Discharge Elimination System permit, to the tribes. Late last year the EPA reissued portions of the permit.
The initial study was conducted in 2003 and the EPA only just issued the final permit last year, eight years later. I wonder if there was any value added to the EPA review?

But is it really the final permit?
Mayer said the commentary on the NPDES operating permit has closed and they are waiting for the final EPA review and issuance.
If the EPA has issued the permit, why is there still talk of a "final EPA review and issuance"? How exactly is the EPA delivering this permit to the company? Or does TAT have the permit but have not yet sent a copy to the company?

Wednesday, January 11, 2012

Another Refinery In the Bakken? -- The Bakken, North Dakota, USA

From Gregg:

Here's a bit of news that surfaced on KXMC at noon.

Tex Hall announces that the Thunder Butte refinery will begin construction this spring near Makoti.

It will be built on about 460 acres (can't remember exact amount). Crude oil will be coming from west of the refinery. They have plans for a pipeline across the lake. There is no link yet for the KXMC story.

http://www.mhanation.com/main/oil_refine.html -- a broken link

A new ink for this story:
The Thunder Butte Petroleum Services Refinery southwest of Minot, ND, might be expanded before ever coming online.
Production in the region is on pace to surpass many early predictions, so the affiliated tribes are considering and expansion before the refinery is in place.
Current plans call for capacity of 20,000 b/d, but the company’s CEO expects wells in the region could produce in excess of 300,000 b/d in the next five years.