Tuesday, December 11, 2018

The CLR Dvirnak Wells In Jim Creek Oil Field Are Being Completed -- December 11, 2018

This page will not be updated.

The Dvirnak wells are being fracked; some are completed. The Dvirnak wells are tracked here.

Note the production profile of one of the Dvirnak wells:
  • 32749, 2,358, CLR, Dvirnak 8-7H, 47 stages; 12.5 million lbs, Jim Creek, t10/18; cum 72K 10/18;
Production profile:
PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN10-20183162410622447163078652715277125
BAKKEN9-20184775176377373826558932372
BAKKEN8-20180000000
BAKKEN7-20180000000
BAKKEN6-20185134013409870179901799
BAKKEN5-20181001468000