Showing posts sorted by relevance for query Golden Pass. Sort by date Show all posts
Showing posts sorted by relevance for query Golden Pass. Sort by date Show all posts

Sunday, May 4, 2025

Golden Pass -- Update -- May 4, 2025

Locator: 48581GP.

March 5, 2025 -- link here. This was the extension that the project needed -- back in March, 2025 -- thank you, Mr Trump and Mr Biden. The FERC commissioners. If I have this correct, three of the four were appointed by President Biden in 2024, and the current chairman was appointed by President Trump during the latter's first term in 2021. Link here.

April 28, 2025 -- within Trump's first 100 days! Another win for Trump. 

Link here.

 ****************************
Golden Pass

For "all"posts on "Golden Pass" on the blog, click here.

From June 21, 2022 -- link here.

Number 8?

  • if Calcasieu Pass was the seventh US LNG export terminal to be built, is Golden Pass #8?
  • Magnolia LNG, Louisiana, would be #9?
    • I remember an "anonymous expert" wrote me in 2015 that just because all these projects were "on the board," there was no guarantee all of them would be built, implying that "we" were all getting way ahead of our headlights. 

US LNG export capacity: link here.

  • record set in 2021, averaging 9.7 billion cubic feet per day = 3.54 trillion cubic feet annually
  • forecast:
  • an increase of 2.4 Bcf/d in 2022 --> a total of 5.94 trillion cubic feet annually
  • an increase of an additional 0.5 Bcf/d in 2023 = 6.44 trillion cubic feet annually

Qatar:

  • capacity to reach 126 million tonnes yearly by 2027
  • current capacity: 77 million tonnes, 2022

Conversion:

  • one million tonnes (LNG) = 48.7 Bcf
  • 77 * 48.7 = 3.750 trillion cubic feet annually
  • 126 million tonnes = 6.136 trillion cubic feet annually

Usual disclaimers apply:

  • there will be typographical and content errors;
  • I often make simple arithmetic errors

Golden Pass, XOM:

  • 18 million tons of LNG per year = 877 Bcf
  • Golden Pass + 2023 US forecast = 0.877 trillion +6.44 trillion = 7.3166 trillion cf/d
  • Golden Pass as percent of current US export capacity: 0.877 trillion / 3.54 trillion = 35%

SPGlobal, June 21, 2022 (today):

A request by the Golden Pass LNG Terminal developer to bring in more workers to build the Texas natural gas export facility is still pending after a year at the Federal Energy Regulatory Commission amid concerns of delay.

FERC staff issued an environmental assessment on March 22 that concluded a Golden Pass plan to boost the peak workforce from 2,900 to 7,700 people per day would not cause significant harm to the environment (CP14-517). But the request still requires approval at a time when FERC is facing pressure over a recent permitting policy overhaul, which commissioners are scheduled to revisit on March 24.

Critics of the policy changes, including gas industry groups and Republican lawmakers, have argued that FERC's new approach will hinder the development of gas infrastructure, even as the White House looks to boost LNG supplies to Europe following Russia's invasion of Ukraine.

Golden Pass told FERC in its original February 2021 request, which also sought to increase traffic volumes and extend construction hours around the clock, that "construction progress would be severely hampered and successful execution of the project would not be feasible" without the regulator's approval for a larger workforce.

Tuesday, June 21, 2022

Update On The Golden Pass LNG Export Terminal At Sabine, TX -- June 21, 2022

Number 8?

  • if Calcasieu Pass was the seventh US LNG export terminal to be built, is Golden Pass #8?
  • Magnolia LNG, Louisiana, would be #9?
    • I remember an "anonymous expert" wrote me in 2015 that just because all these projects were "on the board," there was no guarantee all of them would be built, implying that "we" were all getting way ahead of our headlights. 

US LNG export capacity: link here.

  • record set in 2021, averaging 9.7 billion cubic feet per day = 3.54 trillion cubic feet annually
  • forecast:
  • an increase of 2.4 Bcf/d in 2022 --> a total of 5.94 trillion cubic feet annually
  • an increase of an additional 0.5 Bcf/d in 2023 = 6.44 trillion cubic feet annually

Qatar:

  • capacity to reach 126 million tonnes yearly by 2027
  • current capacity: 77 million tonnes, 2022

Conversion:

  • one million tonnes (LNG) = 48.7 Bcf
  • 77 * 48.7 = 3.750 trillion cubic feet annually
  • 126 million tonnes = 6.136 trillion cubic feet annually

Usual disclaimers apply:

  • there will be typographical and content errors;
  • I often make simple arithmetic errors

Golden Pass, XOM:

  • 18 million tons of LNG per year = 877 Bcf
  • Golden Pass + 2023 US forecast = 0.877 trillion +6.44 trillion = 7.3166 trillion cf/d
  • Golden Pass as percent of current US export capacity: 0.877 trillion / 3.54 trillion = 35%

SPGlobal, June 21, 2022 (today):

A request by the Golden Pass LNG Terminal developer to bring in more workers to build the Texas natural gas export facility is still pending after a year at the Federal Energy Regulatory Commission amid concerns of delay.

FERC staff issued an environmental assessment on March 22 that concluded a Golden Pass plan to boost the peak workforce from 2,900 to 7,700 people per day would not cause significant harm to the environment (CP14-517). But the request still requires approval at a time when FERC is facing pressure over a recent permitting policy overhaul, which commissioners are scheduled to revisit on March 24.

Critics of the policy changes, including gas industry groups and Republican lawmakers, have argued that FERC's new approach will hinder the development of gas infrastructure, even as the White House looks to boost LNG supplies to Europe following Russia's invasion of Ukraine.

Golden Pass told FERC in its original February 2021 request, which also sought to increase traffic volumes and extend construction hours around the clock, that "construction progress would be severely hampered and successful execution of the project would not be feasible" without the regulator's approval for a larger workforce.

Wednesday, October 3, 2018

Natural Gas May Well Be The Story Of The Year -- More Proof -- See RBN Energy Today -- October 3, 2018

Starbucks: arrived at Starbucks about 6:00 a.m. this morning. Happened to be within earshot of three young businessmen working major real estate issues between California and Texas. Their conversation validates everything we seem to intuitively feel regarding the two states when it comes to the economy. Seems the huge movement of Californians (businesses) to this part of Texas (Plano, Frisco, McKinney) continues; perhaps accelerating. Liberal politics in California seems to be scaring businessmen. Marijuana: the individual from California says not eager to getting into marijuana (legal, but it's not legal; lots of regulations); Texas businessmen think marijuana will be huge opportunity in California -- medically legal now. Texas businessmen think using old industrial buildings are perfect for growing marijuana. Argument: local growing (high cost) vs importing from equator. Austin (TX) much bigger challenge for new California business vs DFW. DFW and Austin very different markets; different philosophies. DFW still huge area to grow. Oracle moving into Austin; after 3-hour car tour of Austin bought huge riverside area. Will be 3 - 5 year buildout. Will be huge. Huge Japanese influence. More opportunity in Ft Worth than Austin but Austin has the "bigger" draw. That may change once people start looking at the metrics. Conversation coming down to California vs Texas. In Texas, coming down to Austin vs Ft Worth. Not mentioned: San Antonio; Houston; Odessa-Midland. I had completely forgotten the "bullet train" from Dallas to Houston -- should be operational within next few years. Schwab putting in huge campus just west of DFW; 3,000 Schwabians; already having huge positive effect on local Schwab retail businesses.

Mixmaster: intersection of highways 360, 114, and 121, at the apex of the Dallas, Ft Worth, Grapevine triangle. Starbcks; In 'N Out; new shopping center with millennial focus (we talked about Hopdoddy earlier this week); Texas light rail from Ft Worth to DFW via Grapevine;

Reminder for later: Brent, Equinor, Mariner, Brassey
 ********************************
Back to the Bakken

Wells coming off the confidential list today -- Wednesday, October 3, 2018 --
34664, conf, EOG, Wayzetta 164-23M, Parshall, no production data, 
34261, conf, MRO, Young Woman USA 44-12H, Reunion Bay, no production data,


Active rigs:

$75.23→10/3/201810/03/201710/03/201610/03/201510/03/2014
Active Rigs65573368188

RBN Energy: part 5 -- the experienced, deep-pocketed team behind the Golden Pass LNG project.

Updates

February 1, 2019: COP pulls out of the Golden Pass project; will probably sell its interest to ExxonMobil.

Original Post
It’s crunch time in the race to advance the next-round of liquefaction/LNG export projects along the U.S. Gulf Coast to a Final Investment Decision (FID). And if we’re to assume that only a small number of these multibillion-dollar projects will get their financial go-aheads, it would seem eminently reasonable to put a win-place-or-show bet on a joint venture that includes the world’s leading LNG producer (by far) and one of the largest U.S. natural gas producers — oh, and the partners have very fat wallets too. Size and money aren’t everything, of course, but as we discuss in today’s blog, the team behind the Golden Pass LNG project plans to build its liquefaction trains at the site of an existing LNG import terminal with strong interconnections with coastal pipelines already in place.

2019 will be a pivotal year for the second wave of U.S. LNG export projects. Global demand for LNG continues to rise, and LNG marketers and customers — acutely aware of how much it takes to build new liquefaction capacity — are eager to line up the incremental LNG supply they will need in the early to mid-2020s. Want proof? Royal Dutch Shell, the lead partner in the LNG Canada project, on Tuesday (October 2, 2018) announced a FID on the 14-million-metric-tonnes-per-annum (MMtpa) liquefaction/export terminal in Kitimat, BC. (The project’s other partners are Petronas, PetroChina, Mitsubishi and Korea Gas.)
As it turns out, the U.S. is in many ways one of the best places in the world to locate a new liquefaction/LNG export project. There’s ample natural gas supply in the Marcellus/Utica, Permian and other U.S. plays, an extraordinary network of gas pipelines in place, and a skilled workforce capable of executing these very complicated facilities. By the end of next year, there’s a good chance that at least one new liquefaction/LNG export project will get the financial go-ahead and start construction. More may follow in 2020.
The Golden Pass LNG:
Today, we look at Golden Pass LNG, a joint effort by three global energy powerhouses — Qatar Petroleum, ExxonMobil and ConocoPhillips — to expand their existing LNG import terminal on the Sabine-Neches Waterway near Sabine Pass, TX, into a liquefaction/LNG export facility.
Much like Austin’s East Sixth Street is a mecca for live music and New Orleans’ Bourbon Street is a hub of late-night debauchery, the greater Sabine Pass area (on the border of Louisiana and Texas) already has drawn more than its share of liquefaction/LNG export facilities (Sabine Pass LNG, Cameron LNG and a number of second wave contenders, including Venture Global’s Calcasieu Pass), and for good reason. There’s easy, deep-water access to the Gulf of Mexico and large tracts of waterfront land, but just as important, there are few places on the planet with as many long-haul gas pipelines nearby to deliver large volumes of U.S.-sourced natural gas.
Like most of the initial round of U.S. liquefaction/LNG export projects now in operation or under construction, the Golden Pass LNG site already is home to an LNG import terminal that was developed in the 2000s, when almost everyone was expecting a flood of LNG from Qatar and other foreign sources. Having docks, storage tanks and connecting pipelines in place gives these brownfield projects at least a modest financial leg up over their greenfield-site competitors — their import-related investments were made and paid for years ago.
Qatar Petroleum (which owns 70% of Golden Pass LNG), ExxonMobil (with 17.6%) and ConocoPhillips (with 12.4%) are planning to build three 5.2-MMtpa liquefaction trains for a total of 15.6 MMtpa of capacity. That would require a total of about 2 Bcf/d of natural gas (using a rule-of-thumb ratio of 1 Bcf/d for each 7.6 MMtpa of liquefaction capacity). They also are planning onsite, gas-fired power plants with a capacity of 200 to 250 MW that would provide power for the liquefaction trains and other terminal operations.

Tuesday, February 12, 2019

Three Wells Coming Off The Confidential List Today -- Tuesday, February 12, 2019

Wells coming off the confidential list today -- Tuesday, February 12, 2019: 46 wells for the month; 149 wells for the quarter
  • 34671, drl, Hess, GO-Bergstrom 156-98-2833H-2, Wheelock, no production data,
  • 33103, n/d, CLR, Sakakawea Federal 11-19H1, Elm Tree, t--; cum --;
  • 29403, n/d, Oasis, Seattle Federal 5200 42-35 7B, Camp, t--; cum--;
Active rigs:

$53.692/12/201902/12/201802/12/201702/12/201602/12/2015
Active Rigs63583641137

RBN Energy: Golden Pass FID heats up race for US LNG exports. Pretty cool. We've been following the Golden Pass export terminal pretty closely on the blog.
The dam has broken on the “second wave” of U.S. LNG export projects. ExxonMobil and Qatar Petroleum last week announced a final investment decision on their joint venture liquefaction and export project — called Golden Pass Products — at the brownfield site of the Golden Pass LNG terminal on the Texas side of the Sabine-Neches Waterway. That’s a skipping stone’s throw from Cheniere Energy’s Sabine Pass LNG and Sempra Energy’s Cameron LNG terminals on the Louisiana side of the Gulf of Mexico outlet, as well as a number of other second-wave contenders. With construction slated to begin late next month, the Golden Pass project expects to become operational and begin taking feedgas by 2024. Today, we provide an update on Golden Pass, its potential feedgas needs and how it will be supplied.
2019 is set to be a pivotal year for U.S. LNG exports. Not only is it looking to be a watershed period for liquefaction capacity additions from the first wave of export projects that are already under construction and due online over the next couple of years but it’s also likely to be a milestone year for the second wave of North American export projects as they race toward FIDs. We are tracking 24 of these mostly pre-FID projects, 18 of them along the coastlines of the contiguous U.S.

Friday, February 1, 2019

Too Many Irons In The Fire? Even A Major Oil Company Can't Do It All -- February 1, 2019

Updates

February 6, 2019: project gets "green light."

Original Post 

COP pulls out of import/export terminal, Golden Pass.  RBN Energy had a blog devoted to the Golden Pass story on October 3, 2018.

From oilprice:
Exxon and Qatar Petroleum will proceed with a US$10-billion expansion of their Golden Pass LNG import terminal in Texas to turn it into an export facility as well.
The third partner in the venture, ConocoPhillips, however, will not be joining them in the expansion and has decided to sell the 12.4-percent interest it holds in Golden Pass, the sources also said, adding that Exxon, which has a 17.4-percent stake in the project, is the most likely buyer. Qatar Petroleum is the majority shareholder in the venture with 70 percent.
If interested, be sure to check out the RBN blog on the Golden Pass.

Tuesday, June 21, 2022

Back To Business -- June 21, 2022

Top energy story today: a report that anti-fossil fuel Biden-Granhalm administration is asking XOM to expedite its Golden Pass LNG export terminal in Sabine, TX. Absolutely huge; more below. 

Trending: on my Twitter energy feed --

  • it's all about the European energy crisis
    • Europeans in crisis mode
    • will now do everything to conserve natural gas going into winter 
    • why all the interest in coal? to conserve natural gas
    • quick reading suggests Russian not letting up on squeezing Europe
    • indications Russian ploys are working
  • it's back to coal for Germany, Austria, the Dutch, and likely, the UK
  • Germany committing to long-term LNG contracts with US
  • Groningen to shake again; 
    • if I read this correctly
      • currently, 4.5 bcm produced in CY 2022
      • was to completely end by end of year, CY 2022
      • will now target 2.8 bcm for production year ending October, 2023 
  • Dutch will also remove a cap on production at Dutch coal plants

Investors: usual disclaimers apply

  • OPEC producer says there exists a $30-war premium on the price of oil
    • tea leaves: if truce called, sanctions on Russia will fall faster than Biden's polling
  • oil has fallen so far many companies now at accidental high yields
  • AMZN: interesting analysis over at SeekingAlpha
  • US oil demand: finally, we're going to see a jump
  • anticipate: Biden to announce Federal gas tax holiday before July 4th
    • the gas tax holiday will come too late to save the GDP number for 2Q22
    • having said that, Obama has aid such a holiday -- the gas tax holiday, not the July 4th holiday -- is a "gimmick"

Oil demand: even if demand falls, is that bad for US oil stocks? Just asking.

Domestic LNG

  • US asking XOM to expedite Golden Pass LNG
  • RBN Energy, October 2, 2018; 
  • note: Golden Pass scheduled for 2025
  • September 2, 2021: 
    • Reminder: how the shale revolution changed things. Link here.  Or go directly to this link at Gulf Times:
    • the first liquefaction train of the Golden Pass LNG liquefication and export terminal in Sabine, Texas, a $10bn joint-venture formed by Qatar Petroleum and ExxonMobil, is scheduled to come online by 2024;

International LNG: huge story -- the huge new Qatar export terminal

  • now, XOM joins the partnership.
    • others: COP, Eni, and TotalEnergies
  • this expansion, previously announced, will increase Qatar's LNG capacity to 110 million metric tons / year vs 77 million currently
  • memo to self: find Texas/Louisiana LNG export capacity once Golden Pass on line

*****************************
First Day Of Sailing School

Thursday, February 7, 2019

Wow, Wow, Wow! Golden Pass Contract Goes To BHGE -- February 7, 2019

Link here.
Baker Hughes, a GE company (BHGE) reported Thursday that it will supply turbomachinery equipment for the construction of the Golden Pass LNG export facility in Sabine Pass, Texas.
Partners ExxonMobil Corp. and Qatar Petroleum announced Feb. 5 that they had decided to proceed with Golden Pass and expect to break ground on the $10 billion-plus project this quarter. The companies have also awarded a joint venture of McDermott International, Inc., Chiyoda International Corp. and Zachry Group the mega-contract to build the facility, which will produce approximately 16 million tons per year of liquefied natural gas (LNG).
BHGE will supply turbomachinery equipment for three LNG trains, including six gas turbines and 12 centrifugal compressions. 
 Golden Pass LNG export facility vision: to be best in class.

Friday, May 17, 2013

US Allows LNG To Be Exported To Countries That Do Not Have A Free Trade Agreement With The US; XOM/Qatar Moving On Golden Pass LNG Export

Oil & Gas Journal is reporting:
The US Department of Energy conditionally approved Freeport LNG’s request to export domestically produced LNG from its Quintana Island, Tex., terminal to countries that do not have a free trade agreement with the US.
The conditional authorization allows exports up to 1.4 bcfd for 20 years and is subject to environmental review and final regulatory approval. DOE approved Freeport’s application to export LNG from the terminal to FTA countries on Feb. 11.
The May 17 announcement was DOE’s second LNG export approval to non-FTA countries; its first for as much as 2.2 bcfd of gas came earlier in May to the Sabine Pass terminal in Cameron Parish, LA.
Several oil and gas associations applauded DOE’s move. “One export permit is a step in the right direction, but many more job and revenue creating projects are still waiting for approval,” said Erik Milito, the American Petroleum Institute’s upstream and industry operation’s director.
Reuters also reports the story. Reuters says the amount of natural gas exported will equal about 2% of total US production (at current levels). Two percent. Remarkable. Lots of questions remain.

The article also notes that there is a small window to get these export facilities built: other countries, like Australia are moving very fast on their own export facilities.

Is that cool or what, though, exporting natural gas?
***********************

Meanwhile, remember Golden Pass? Exxon and Qatar?

The joint venture is advancing its permit application for LNG export.

The Oil & Gas Journal is reporting:
Golden Pass Products LLC has taken its first step toward seeking US Federal Energy Regulatory Commission permission to build the 15.6 million-tonne/year LNG export terminal it plans at Sabine Pass, TX.

The company, a venture of Qatar Petroleum International and ExxonMobil Corp., which operates an LNG import facility at Sabine Pass, ....
It has received Department of Energy approval to export LNG to countries with which the US has free-trade agreements and earlier this month announced signing of a commercial framework agreement for sale of all the proposed facility’s output.

Is that cool or what?

Wednesday, October 12, 2016

List Of Potential US LNG Export Facilities -- RBN Energy -- October 12, 2016

Sources

Port Arthur, TX: Sempra, Saudi Aramco -- joint ventures and expansions. Update: on hold -- May 22, 2020.

EIA: US liquefaction capacity additions by project and train, release date -- March 2, 2017

Updates

Cameron: to expand; update; Sempra, April 4, 2022.

Driftwood: near FID.

How close is Cheniere to FID on further expansion, March 8, 2022. 

Cheniere has sold out all LNG through 2040, March 7, 2022.

Sabine Pass train 6 commissioned, November 1, 2021.

US LNG: FERC authorizes / okays feedgas flows to Sabine Pass train 6. Link here. 

September 19, 2021: Cheniere Energy, Inc: asked for FERC approval for a sixth train at Sabine Pass LNG in Louisiana. Approval was requested by Tuesday, September 21, 2021 (good luck with a Dem-dominated FERC). Train 6 is expected to be complete in 1Q22. Link here.

September 2, 2021: Golden Pass, Sabine; first liquefaction train; joint venture, Qatar and XOM; in-service, 2024. Link here.

August 26, 2021: US LNG exports smashing records.

May 18, 2021: update of export terminals. 

March 19, 2021: US LNG feedgas demand sets another all-time record. Venture Global LNG's Calcasieu  Pass terminal, Louisiana, slated to ship first cargo later this year. Cal-cashew.

March 16, 2021: floating liquefaction natural gas export terminals. At same link, Gibbstown, NJ.

November 12, 2020: Calcasieu Pass update. Huge story.

August 31, 2020: contractor to resume construction at Sabine Pass' Train 6 and the Third Berth project following Hurricane Laura one week ago.

August 13, 2020: update on Tellurian's Driftwood facility here.

May 22, 2020: Sempra Energy delays decision on Part Arthur, TX, project. Saudi Arabia delays decision on securing five huge LNG tankers scheduled for loading in 2025. Link here.

May 20, 2020: Cameron's train 3 starts producing LNG; Hackberry, LA.

September 9, 2019: behind schedule? In the graphic above, EIA shows Cameron to have "T3" by 3Q19. A couple of weeks ago, SRE announced that the first train of the Cameron LNG liquefaction-export project had initiated service, located in Hackberry, LA. The article does confirm that the Cameron facility will have three trains. It's hard to say from the story, but it sounds like the capacity of all three trains combined is 12 million tonnes per annum of LNG, or nearly 1.7 billion cubic feet per day. Conversion at this site.

September 4, 2019: Cheniere declares 2nd train at CC completed; this marks Cheniere's 7th train at CC and Sabine Pass; a 3rd train at CC under construction; estimated completion, 2H21; at Sabine Pass, Cheniere has announced it will build a sixth train. Total now projected: 9. Note: in the graphic above only five trains were projected as of 3Q19.

June 3, 2019: Cheniere to add 6th train at Sabine Pass, Louisiana. Note: in the graphic above only five trains were projected as of 3Q19.

May 30, 2019: of all the proposals in the original list, the most prominent one likely not to proceed any time soon is the G2 LNG proposal for a liquefaction/LNG export facility; up to 14 MTPA; Cameron Parish; according to a 2019 - 2010 Louisiana Economic Outlook white paper.

May 30, 2019: update on the Rio Grande LNG project at this post; this project was on the original list (scroll down).

May 29, 2019: three new LNG export facilities near New Orleans, LA; Venture Global; two of the three were in the original list below;

May 23, 2019: update -- Sempra Energy begins operations at its Cameron export terminal. 

May 6, 2019: update -- Sempra's Port Arthur LNG wins federal "okay" to start exports. SeekingAlpha -- can export to countries that don't have a free trade agreement with the US; SRE can export almost 2 billion cfpd; two liquefaction trains. SRE to make FID later this year.

April 19, 2019: update -- a Florida project hits a milestone; Tellurian and Sempra updated.

February 11, 2019: update -- link here -- 


April 16, 2019: SRE's Cameron LNG has begun pipeline feed gas flow to the first liquefaction train of the liquefaction-export project as it prepares to begin production of liquefied natural gas (LNG) at the facility in Hackberry, La. This is the final commissioning step for Train 1 of Cameron LNG Phase 1.

December 16, 2018: Qatar plans to expand.

November 2, 2018: Cameron/SRE/Louisiana -- commissioning process begins.

August 14, 2018: Cheniere ready to fire up its second LNG export terminal; Corpus Christi; will be country's third export terminal; many others under construction. If you add up the capacity in the graph above dated March 2, 2017, it adds up to 7.1 Bcf/day. Now, Platts estimates 4 Bcf/day by the end of the year (2018) and 8 Bcf/day by the end of 2019.

May 23, 2018: see November 14, 2017, update below. Cheniere okays third train at Corpus Christi.

November 21, 2017: Tellurian will build a 20 train LNG facility on Lake Charles for $15 billion ... half the historical price for these plants. The LNG project is the Driftwood, being built by Bechtel.

November 14, 2017: Cheniere to make investment decision over a third planned liquefaction train at its Corpus Christi terminal. 

November 4, 2017: Dominion's Cove Point should be up and running this week. 

October 27, 2017: update of Sabine; 4th train completed. Pretty awesome. 

September 18, 2017: FERC approves Kinder Morgan's Savannah, Georgia, Elba Island LNG export terminal.

May 6, 2017: update. Texans for Natural Gas said in a report that seven LNG export projects proposed or under construction in the state could raise $20 billion or more in tax revenue, create more than 135,000 jobs and have a total economic impact of roughly $145 billion.

April 30, 2017: RBN Energy update. Archived.
  • Cheniere Energy's Sabine Pass, southwestern Louisiana: three liquefaction trains are operating; a fourth is gearing up to run; a fifth is nearing completion
  • Alaska: newly filed plan by state-owned Alaska Gasline Development Corp to develop a $40-billion-plus LNG export project; would include an 800-mile gas pipeline from Prudhoe Bay to Nikiski, AK; three liquefaction trains at Nikiski; two export loading docks
  • second-wave proposals (similar to first-wave projects now in operation at Sabine Pass ; Cameron LNG, Louisiana; Dominion's Cove Point LNG, Maryland; Freeport LNG and Cheniere's Corpus Christi LNG, Texas; all projects feature liquefaction trains with capacities between 4 and 5.2 MTPA each; most are located at existing LNG import terminals, eliminating some of the port-related costs that projects at greenfield sites would face
  • Brownsville, TX; and, Texas City, TX: NextDecade LLC's; the tried-and-true approach; each site would have several 4.5-MTPA trains; online in the early 2020s
  • Texas LNG Brownsville LLC: a second category of second-wave projects; smaller-scale proposals; trains would have capacities of 1 to 2 MTPA each; at Brownsville: plans to build two 2-MTPA liquefaction trains; some appeal; more interest since first announced
  • Another second-wave example: Cheniere's plan to build seven 1.4-MTPA trains to meet the incremental LNG needs of international LNG buyers
  • Veresen's Jordan Cove project, Oregon: up to five 1.5-MTPA trains
  • third category: the Alaska LNG proposal; would require installing some 800 mies of new, 42-inche-diameter pipeline across Alaska
March 4, 2017: update on Texas LNG (Third Point LLC / Samsung consortium) mentioned in the original post below.

February 1, 2017: Louisiana's Port Fourchon may add LNG terminal, over at Rigzone.

January 28, 2017: Exelon has applied for an LNG export facility permit for Brownsville, TX. 

November 28, 2016: from FuelFix -- see 5th bullet below -- "Tellurian Investments / Driftwood LNG" -- GE has invested a $25 million equity stake in Tellurian Investment's Driftwood LNG project.
 
Original Post
 
The list of US LNG export projects at various points along the regulatory process, as reported by RBN Energy. First, Louisiana, mostly near Lake Charles:
  • Cheniere: to build a sixth 4.5 MTPA liquefaction train at Sabine Pass LNG site
  • Cameron LNG: has proposed two additional 4.5-MTPA liquefaction trains at its Hackberry facility south of Lake Charles, LA
  • Lake Charles LNG: has proposed a three-train, 16.2-MTPA liquefaction/LNG export facilty in advanced stages
  • LNG Ltd: has proposed the development of the Magnolia LNG project; as many as four 2-MTPA liquefaction plants, near Lake Charles [Update, DOE approved, December 2, 2016]
  • Tellurian Investments: developing Driftwood LNG, total capacity up to 26 MTPA; also near Lake Charles
  • Louisiana LNG Energy LLC: has proposed construction of a 6-MTPA liquefaction/LNG export terminal on Mississippi river southeast of New Orleans
  • Venture Global LNG: two proposed liquefaction/LNG export terminals in Louisiana; one 20-MTPA facility and one 10-MTPA facility
  • Southern California Telephone & Energy: developing the Monkey Island liquefaction/LNG export project; south of Lake Charles; at least three 4-MTPA trains
  • G2 LNG: has proposed a liquefaction/LNG export facility; up to 14 MTPA; Cameron Parish
  • CE FLNG: proposed project; two floating LNG vessels; each vessel up to 4 MTPA
Now, Texas:
  • Cheniere: plans to build three more 4.5-MTPA liquefaction trains at its Cheniere's Corpus Christi facility
  • Freeport LNG: developing a possible fourth 4.4-MTPA train at its Freeport site; completed; online December 16, 2016;
  • Port Arthur LNG, an affiliate of Sempra: leading the development of a proposed two-train, 10-MTPA liquefaction/LNG export terminal along the Sabine-Neches Waterway in Port Arthur; Woodside Petroleum is also participating in this project
  • Annova LNG: has proposed a six-train, 6-MTPA liquefaction/LNG export facility planned by Exelon Generation for Brownsville
  • Third Point LLC (a NYC-based investment fund) and Samsung Engineering are developing Texas LNG, a proposed 4-MTPA liquefaction/LNG export terminal in Brownsville
  • Golden Pass LNG: a joint venture of Qatar Petroleum and Exxon Mobil; a 15.6 MTPA plant at its existing LNG import terminal at Sabine Pass
  • Rio Grande LNG, being developed by NextDecade LLC: up to six 4.5-MTPA liquefaction trains and two LNG loading berths along the Brownsville Shipping Channel
In other states:
  • Kinder Morgan: two 5-MTPA trains in Pascagoula; and, a 2.5-MTPA Elba Island project in Chatham County, GA (near Savannah, Georgia)
  • Veresen: a proposed 6-MTPA Jordan Cove LNG project in Coos Bay, OR
  • Maryland, Cove Point (not mentioned in this RBN article)
Bottom line:
  • those projects would add more than 220 MTPA of capacity
  • those projects would require more than 30 billion cubic feet of gas / day
  • it's safe to say, according to RBN Energy, that most of these projects will never get to the FID stage
  • RBN Energy: does not imagine more than a few new liquefaction trains would be financed and built by by the mid-2020s

Wednesday, February 6, 2019

Keeping Texas Great -- Making America Great Again -- February 6, 2019

Oh by the way, did you all see the most recent "trade deficit" numbers? From CNBC no less.


Now back to the keeping Texas great / making American great again --- that $10-billion Texas LNG project gets the "green light," as they say. From the Rigzone staff, data points:
  • Golden Pass LNG export project -- BHGE gets the contract.
  • Sabine Pass, TX
  • partners: ExxonMobil (30%) and Qatar Petroleum (70%)
  • the companies formally announced their decision at a ceremony Tuesday in Washington, D.C., in the presence of U.S. Secretary of Energy Rick Perry, Qatar’s Minister of State for Energy Affairs Saad Sherida Al-Kaabi and other officials
  • won't be the last Qatar investment in the US
  • part of Qatar's announcement to invest $20 billion in the US energy sector
  • Golden Pass will produce 16 million tons of LNG/year
  • construction: 9,000 jobs
  • 200+ permanent jobs
  • COP had been part of the original deal, but pulled out
Note: DOE has granted Golden Pass LNG authorization to export to countries that have free trade agreements with the United States as well as those that do not, according to the project website. In addition, the project received authorization from the Federal Energy Regulatory Commission in 2016.

Sunday, November 20, 2022

US LNG Export Terminals -- An Update On The Race -- Golden Pass, Plaquemines, Cheniere Expansion -- November 20, 2022

Updates

December 15, 2024: Plaquemines up and running. Link here. 

December 19, 2022: update. 

Original Post 

Link here. Right now, this article is not behind a paywall at this link. The story is behind a paywall at Bloomberg. 

A must-read article for those interested in US LNG exports.

US LNG export terminals are tracked here.

The "list" tag.

Archived.

The article is too long to summarize on NFL Sunday, but this is what will be covered in depth at the linked article at the top.

While the US filled some of the supply gap by exporting huge quantities of liquefied natural gas from its seven plants, global markets are going to have to wait at least two more years before any new LNG supplies from the US come online. Three large-scale projects requiring more than $30 billion of financing are now under construction in Texas and Louisiana, yet none will be ready next year.

Two of the projects, Golden Pass LNG near Port Arthur, Texas, and the first phase of Plaquemines LNG, along the Mississippi River about 25 miles south of New Orleans, are expected to begin production in 2024, setting up a race to see which will be the eighth US export terminal. The third project, by Cheniere Energy, the US’s largest LNG exporter, will expand an existing plant in Corpus Christi and won’t begin production until late 2025.

Natural gas traders, government officials and industry observers will spend the next few years watching the projects for any signs of delay or movements ahead of schedule.

Golden Pass is a joint venture between industry titans Qatar Energy and Exxon Mobil. It began construction in May 2019.

Plaquemines, a project by the closely held Virginia-based developer, Venture Global LNG
, quietly started construction in August 2021. Venture Global pulled off a near-miracle in January 2022 when it began production at its first LNG plant, Calcasieu Pass in Cameron, Louisiana, in a record 29 months after securing financing. Many wonder if it can repeat or beat that success with Plaquemines.

I still remember, vividly, the day I first wrote about all these US LNG export terminals that were planned -- that might have been ten years ago -- and getting a note from a reader who suggested it was all "pie in the sky," wouldn't happen. 

That reader never anticipated the European energy crisis -- another story that was "predicted" on the blog back in 2013 and did not anticipate the amount of natural gas that would be produced by the Bakken revolution. Amazing how things turned out. 

By the way, both the EU and Saudi Arabia saw this coming even if a lot of Americans did not.

Friday, April 28, 2017

Two More US-LNG-Export Stories -- April 28, 2017; Look At the Number Of Jobs One LNG Export Facility Will Generate -- President Obama, What Were You Thinking?

This past week has been an incredible week for LNG and the US and exports. Here are two more stories sent to me by a reader:

Cheniere ships LNG to Poland as Europe seeks less reliance on Russian gas. From FuelFix. Data points:
  • will be first shale gas to a member of the former Soviet bloc
  • Europe seeks to cut its dependence on fuel from Russia
  • this is the first such contract for Central and Eastern Europe
  • no LNG has been shipped to northern Europe since Sabine Pass started exports more than a year ago
  • Poland may offer a new outlet for Cheniere
For those with a long memory, Poland put too many obstacles in the way for E&P operators to explore for shale gas in their own country (I believe it was ExxonMobil that inally gave up trying; this was not that many years ago; within the lifetime of the blog).

By the way, where is Sabine Pass shipping US LNG? Glad you asked. From that link from Bloomberg:


Second story: Golden Pass LNG cleared to export, also at FuelFix. Data points:
  • DOE approved
  • up to 2.21 billion cubic feet of gas per day
  • located outside Sabine Pass, was originally built to import LNG from abroad in 2009
  • following the Bakken boom (memo to Jane Nielson), a joint venture between Qatar Petroleum, ExxonMobil and ConocoPhillips shifted gears
  • the number of export facilities continues to grow; now there are seven under construction; another four that have been approved but not yet begun
  • US SecEnergy Rick Perry gives the credit to President Trump
  • Golden Pass not yet completed
  • will provide 45,000 direct and indirect jobs over five years; another 3,800 direct and indirect jobs over the next 25 years  
Meanwhile, no new jobs under President Obama, but now he's giving speeches that fetch him $400,000. To date: one. Another one scheduled. Even Pocahontas expressed concern.

Friday, May 10, 2013

Proposed Joint Qatar - Exxon LNG Exporting Terminal In Texas

Remember this past winter, how cold it got in Great Britain (notwithstanding all that global warming talk); the island nation ran dangerously close to running out of natural gas (they killed the coal industry under Thatcher).

Qatar and Exxon hope to build a LNG export terminal in Texas specifically to answer Great Britain's needs. Maybe that's why President Obama went down to Texas this week, to see how the project was coming along. He should approve it; the terminal is 70% owned by the Arabs.

The (London) Globe and Mail is reporting, which explains the incorrect spelling:
Under the deal, the companies would send up to 15.6 million tonnes of LNG each year to their South Hook terminal in Wales from the Golden Pass plant in Texas, pending U.S. government approval to build the plant and export LNG.
The Golden Pass LNG Terminal is owned by Golden Pass LNG, a joint venture formed by affiliates of three of the world’s largest and most experienced oil and gas companies. Qatar Petroleum (70%), ExxonMobil (17.6%) and ConocoPhillips (12.4%).

Wednesday, May 14, 2025

"We Own 70% Of That" -- Qatar -- Golden Pass -- Update -- May 14, 2025

Locator: 48582GP.

Updates

May 14, 2025: Golden Pass update. Link here.

Golden Pass #LNG timing update.

"We [Qatar] own 70% of that. But these projects take time to actually deliver and we expect first LNG to come by the end of this year (2025) and hopefully to inaugurate officially the project in the 1st qt of 26,"  Qatari Energy Minister.
.

This is for Train 1 of 0.68 bcf/d. No ETA for Train 2 and Train 3 start.

That $400 million Boeing? Probably paid for in several weeks. LOL.  Best part? Trump living rent-free in Schumer's brain.

Original Post 

From March 4, 2025:

March 5, 2025 -- link here. This was the extension that the project needed -- back in March, 2025 -- thank you, Mr Trump and Mr Biden. The FERC commissioners. If I have this correct, three of the four were appointed by President Biden in 2024, and the current chairman was appointed by President Trump during the latter's first term in 2021. Link here.

April 28, 2025 -- within Trump's first 100 days! Another win for Trump. 

Link here.

Monday, May 2, 2022

Updating The US LNG Export Terminals Graphic -- May 2, 2022

Updates

June 3, 2022: RBN Energy with huge update. 

May 20, 2022: Freeport LNG has requested a 26-month FERC extension to place its 5.1-million tpy Train 4 in service. New requeested deadline is August 1, 2028. Link here, though link may break over time.

May 5, 2022: Sempra, FID for fourth train at Cameron on track; decision to be made 2023.

May 3, 2022: EIA --  number 7 -- this should be driving the faux environmentalists nuts -- I'm not sure if the Biden administration knows that oil and natural gas are pretty closely related --

 Original Post

I saw the headline. Had no interest in reading the story. I knew what it was all about just from the headline. But several hours after seeing the headline I finally decided to check out the article by Julianne Geiger.

I'm glad I did. I didn't care about the actual story. What interested me was the "update" of the US LNG export terminal story that began in 2016. 

That story is absolutely fascinating. Prior to 2016, the US wasn't building LNG export terminals, it was building import terminals. But then things changed. I honestly don't remember the tipping point -- I assume it was the Permian and the Eagle Ford. They were producing so much natural gas -- on top of the fields/plays in Appalachia that the US no longer needed to worry about natural gas. Wow, what a turn of events. But I digress. 

[There is some irony here. At the time the US/FERC was questioning whether to approve these projects and the developers were deciding whether to make the final investment decision to go ahead with building them, little did they know what would transpire in 2022 -- Putin's War -- pure serendipity.]

[More irony: now that diesel if trending toward $6 / gallon, and gasoline is trending toward $5 / gallon, it's a shame that the Keystone XL was canceled. By itself, "we" might still be where "we" are today with very expensive gasoline, but "killing the Keystone" has become a metonym for Biden's efforts to curry favor with the "greens": "killing the Keystone" is a metonym for all the obstacles Washington (DC) is putting ii place to kill the North American oil sector: the killing the Keystone XL, banning new drilling on federal land, slow-rolling fracking on federal land, adding new environmental regulations for future pipelines, etc.]

Back to the linked article.

Soaring demand for U.S. LNG has now rebooted export projects that had previously languished, and the Biden administration has approved new export licenses for projects under development.

Last week, the Biden administration authorized more LNG shipments from two U.S. plants under development. The move came as Russia cut off gas to Poland and Bulgaria for refusal to pay in roubles.

One of those plants is Texas-based Golden Pass LNG, which is owned by Exxon and Qatar Petroleum and is expected to go online in 2025. The second is the Louisiana-based Magnolia LNG, owned by Glenfame Group LLC and expected to launch in 2027.

Another factor adding to U.S. LNG exports in the coming months will be the ramp-up launch, on April 29, of the Louisiana-based Calcasieu Pass export terminal, which is the seventh export terminal to begin production in the United States since 2016. This terminal can turn around 3.1 billion cubic feet per day, according to the EIA, with two shipping berths that can load up to 185,000 cubic meters.

Calcasieu shipped its first LNG on March 1st, and natural gas deliveries to the terminal have steadily increased since the beginning of the year. Three blocks are still awaiting approval at this plant, expected by year’s end.
So, there's the update. 

" ... the Louisiana-based Calcasieu Pass export terminal, which is the seventh export terminal to begin production in the United States since 2016."

Remember this graph? 

There they are, the seven terminals, several with multiple trains or phases. 

And, I never noticed it before, but this is where Ms Geiger got her data point, the seventh export terminal since 2016. Pretty cool.

So, now we have to update that graph -- to add the Golden Pass LNG (Texas) and the Magnolia LNG (LA) export terminals. RBN Energy has gone over the export terminals in much great detail, but seeing that graph again and correlating it with Ms Geiger's story sort of brings it all together for me.

The graph at the above link, updated:

Monday, December 30, 2024

Definitely Not A Manic Monday -- December 30, 2024

Locator: 44569B.

Some love for Linda Lavin, link here:

LNG update: with Cheniere's 1.4 Bcf/d Corpus Christi III (#8) now on line, what's next:

  • QatarEnergy/ExxonMobil’s 2.4-Bcf/d Golden Pass LNG (#9) in Sabine Pass, TX, which will start coming online in the first half of 2025; 
  • Sempra's 0.43 Bcf/d Energía Costa Azul (ECA) LNG Phase 1 in west Mexico, to start up in spring, 2026 (this is a delay, had been scheduled to go online summer of 2025); update, June 6, 2026: production has begun. Links everywhere.
  • NextDecade Corp.’s 2.3-Bcf/d Rio Grande LNG (#10) in Brownsville, TX, starting up in 2027; and,
  • Sempra and ConocoPhillips’s 2-Bcf/d Port Arthur LNG (#11), coming online in 2027-28.

*********************************
Back to the Bakken

WTI: $71.05.

New wells reporting:

  • Tuesday, December 31, 2024: 51 for the month; 154 for the quarter, 682 for the year
    • None.
  • Monday, December 30, 2024: 51 for the month; 154 for the quarter, 682 for the year
    • None.
  • Sunday, December 29, 2024: 51 for the month; 154 for the quarter, 682 for the year
    • None.
  • Saturday, December 28, 2024: 51 for the month; 154 for the quarter, 682 for the year
    • 40731, conf, Rockport Energy, Camden 10-3 3H,
    • 39499, conf, Enerplus, Brown Bear 158-99-36-25-5H, 
    • 37664, conf, BR, Kellogg Ranch 1A TFH, 

RBN Energy: Gray Oak stands out as the only Permian crude pipeline to greenlight an expansion. Archived.

As crude oil production in the Permian continues to grow and pipelines from West Texas to the Gulf Coast edge closer to full utilization, it’s becoming a challenge for producers and shippers alike. Amid this capacity crunch, one pipeline stands out as the only one with a detailed expansion plan: the 850-mile, 900-Mb/d Gray Oak Pipeline from West Texas to Corpus Christi and Sweeny, TX, which started up in late 2019 and became fully operational in early 2020. In today’s RBN blog — the latest in our series on Permian crude oil pipelines — we discuss Gray Oak Pipeline’s dynamic story, including its shifting ownership, strategic connectivity and expansion plans.

In Part 1 and Part 3 of this series, we looked at Longhorn Pipeline and BridgeTex Pipeline, respectively, and what ONEOK has accomplished with these systems since it acquired Magellan. In Part 2, we looked at EPIC’s Crude Pipeline to the Corpus Christi area, which has been operating at full capacity. Today, we’ll cover Gray Oak.

We’ll begin by noting that Gray Oak started up shortly before crude oil demand cratered as the pandemic hit. In response, Permian producers shut in a significant amount of production during the summer of 2020. Additionally, two other new Permian pipelines — also to Corpus Christi — started up during the second half of 2019: Plains All American’s Cactus II (585 Mb/d) and EPIC Crude (400 Mb/d, expanded in 2020 to 600 Mb/d), resulting in a glut of crude pipeline egress.

Despite these challenges, Gray Oak’s outflows quickly ramped up throughout 2020. As shown in Figure 1 below, Gray Oak has operated near its 900-Mb/d capacity (dotted horizontal black line) for some time now. Earlier this year, Gray Oak Pipeline LLC sanctioned a 120-Mb/d expansion following a successful open season. Contracted volume commitments of 80 Mb/d start in April 2025 and one year later another 40 Mb/d is committed to the pipe. Gray Oak could offer early service for new or existing shippers if capacity is desired sooner.

Gray Oak Outflows  

Figure 1. Gray Oak Outflows. Source: RBN Crude Oil Permian

The ownership journey of Gray Oak Pipeline is complicated, to say the least. When the project was in its planning stage, Phillips 66 (P66) held a 75% stake and refining company Andeavor owned the remaining 25%. In 2018, Marathon Petroleum acquired Andeavor for $23 billion, inheriting its 25% stake in Gray Oak (box #1 in Figure 2 below), along with a similar stake in the South Texas Gateway (STG) export terminal in Ingleside, across the bay from Corpus. (More on that later ­— spoiler alert: STG’s traded hands a couple of times since then.) We should note that Andeavor and its old Andeavor Logistics master limited partnership (MLP) had its own intricate corporate history with Marathon and its MPLX unit.

Much, much more at the link. 

*********************************
Cheniere

December 30, 2024: Cheniere produces first LNG at Corpus Christi, stage III, link here.

April 16, 2024, flashback:

From RBN Energy, today: new JV's focus is moving Permian natural gas to LNG export terminals. Archived here.

Projects already approved / permitted by the US government ...  expected to increase U.S. LNG export capacity to about 25 Bcf/d from the current 14 Bcf/d.

Of that 11 Bcf/d of incremental capacity, more than 8 Bcf/d will be sited along the Texas coast.

These projects include Cheniere Energy’s 1.4-Bcf/d Stage III at Corpus Christi LNG, which is scheduled to begin starting up late this year; QatarEnergy/ExxonMobil’s 2.4-Bcf/d Golden Pass LNG in Sabine Pass, TX, which will start coming online in the first half of 2025; NextDecade Corp.’s 2.3-Bcf/d Rio Grande LNG in Brownsville, starting up in 2027; and Sempra and ConocoPhillips’s 2-Bcf/d Port Arthur LNG, coming online in 2027-28.

All the way back to 2017:


Friday, April 3, 2026

Golden Pass LNG, Texas, Set To Load First Export Cargo Amid Record Feedgas Intake -- April 3, 2026

Locator: 50416LNG.

Article at link was posted by Hart Energy on April 2, 2026.  

The LNG tanker HL Sea Eagle is expected to arrive at the Golden Pass export terminal in Texas on April 20 to load the plant’s first cargo of liquefied natural gas (LNG) for export, according to a trading source and LSEG ship-tracking data.

******************************
The Book Page

Completed my notes on Volume 2, Norman Sherry's biography of Graham Greene. 

Link here. 

************************
Movie Night

Graham Greene's The Third Man. Perhaps one of the best movies ever. Others agree; from wiki:

In 1999, the British Film Institute voted The Third Man the greatest British film of all time. In 2011, a poll for Time Out ranked it the second-best British film ever. 

It seems like a movie in which Orson Welles would have written the screenplay, acted in, and directed. And, yet, only one of the three was true -- Orson Welles played Harry Lime in the movie, and that was it. And on-screen he had less than eleven minutes.

Excellent movie. 

On the other hand Graham Greene's Our Man in Havana was a big disappointment. It was completely miscast. The lead needed to be played by Peter Sellers, had the latter been ten years older. Alec Guiness was either too old (possibly) or completely misread the play (hard to believe). The director of both movies: Carol Reed. The movie's premise (and the book's premise, of course) was brilliant, and based on factual events.

Monday, March 30, 2026

Golden Pass -- March 30, 2026

Locator: 50368QATAR.

Comment: this LNG story is really quite fascinating! 

Golden Pass (US export terminal) will more than make up for any LNG loss from Qatar the country, if I'm reading the links below correctly. How quickly the US becomes the largest LNG exporter. Truly amazing.

A reader sent me a note earlier today: how Europe has fallen so far behind in the energy producing sector; in fact, Europe has fallen even further behind in AI investment. Europe has become not much more than a tourist destination for Americans.

Link here. 

To be completed later, but here are the links:


 

Link here. 

Posted earlier: