Re-Entry -- Initial Production Extrapolates To 117K BBls Over 30 Days -- BR -- #17309 -- Washburn, Charlson -- March 7, 2026

Locator: 50167B.

The well

  • 17309, AL/TA/270, BR, Washburn 44-36H, Charlson, t7/08; re-entered, 4/25; cum 266K 1/26; first month after re-entering: 23K.
    • offline for five years; in 2020 down to <400 bbls / month;
    • back in production 4/25; 23,371 bbls over 6 days extrapolates to an astounding 116,855 bbls crude oil over 30 days
      • originally drilled back in 2008; 
      • re-entry process started on August 23, 2024; 
      • after reaching the total depth of the original hole, the planned extension of the well began drilling at 1415 hrs CT August 27, 2024. 
      • the extension was drilled to TD of 20,496' MD on August 28, 2024. 
    • the rig was then walked to the next well on the pad (most likely #40566; the third well on this 3-well pad was #40567). 

Production profile:

PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN1-2026309865986679036633465961289
BAKKEN12-2025269725967668934857948227284
BAKKEN11-202530109271100279685894958537329
BAKKEN10-202531123071222578025784957242521
BAKKEN9-2025269059908058323639636060273
BAKKEN8-2025291613416122107095064750075492
BAKKEN7-202520119661199868563430733902357
BAKKEN6-2025232014920022133984971749037620
BAKKEN5-2025623371234001540946666432893357
BAKKEN4-2025535213390250258085689107
BAKKEN3-20253006514000
BAKKEN2-20250000000
BAKKEN3-20200000000
BAKKEN2-2020600175600
BAKKEN1-20202131928536648405191
BAKKEN12-20193121024984700306317
BAKKEN11-20193025726773381191116
BAKKEN10-201911312255214080381
BAKKEN9-2019178302534128712
BAKKEN8-2019291752357950439438
BAKKEN7-20193121726511034417691
BAKKEN6-2019292192309337926542