In today's daily activity report, CLR with ten new permits, #39328 - #39337, inclusive:

  • 39328, conf, CLR, Arthur 6-12H, Little Knife,
  • 39329, conf, CLR, Arthur 7-12H1, Little Knife,
  • 39330, conf, CLR, Arthur 8-12H, Little Knife,
  • 39331, conf, CLR, Arthur 9-12H1, Little Knife,
  • 39332, conf, CLR, Arthur 10-12H, Little Knife,
  • 39333, conf, CLR, Hegler 6-13H, Little Knife,
  • 39334, conf, CLR, Hegler 7-13H1, Little Knife,
  • 39335, conf, CLR, Hegler 8-13H, Little Knife,
  • 39336, conf, CLR, Hegler 9-13H1, Little Knife,
  • 39337, conf, CLR, Hegler 10-13H, Little Knife,

The wells, location:

  • Hegler wells, SWSE 12-146-97; to be sited 323 FSL and between 2626 FWL and 2453 FWL
  • Arthur wells, SESW 12-146-97; to be sited 324 FSL and between 2401 FWL and 2581 FWL;

The graphics, pending



Existing wells:

  • 18748, 718, CLR, Arthur 2-12H, Little Knife, t9/10; cum 241K 8/22;
  • 18747, 689, CLR, Hegler 2-13H, Little Knife, t9/110; cum 261K 8/22;
  • 18513, 714, CLR, Arthur 1-12H, Little Knife, t9/10; cum 149K 8/22;
  • 18515, 418, CLR, Hegler 1-13H, Little Knife, t9/110; cum 149K 8/22;