March 30, 2022: from a reader; the reader's thoughts and my thoughts --
- Patterson 280 rigging is coming down today
- all wells drilled to depth
- the rig was a walking rig
- back and forth, the rig drilled the four wells to KOP
- once KOP reached in all four wells, rig walked back to complete the laterals
- some of this is fact; some conjectural; explains everything
Original Post
From a reader:
If you want to solve a real head scratcher figure out why Patterson 280 has been on the Murex Borstad 3 well pad all winter. I may be wrong but the way the rig is oriented on location leads me to believe they could still be on the first hole.
I drive past it at least 2x per day and there is little activity and there's always pipe in the derrick like they're tripping.
I'll come back to this one later. I don't have any news, but I need to spend some time on it. Later, some data:
The wells:
- 38598, conf, Murex, Sheldon Mark 34-22H-A 3MB, Tioga, no production data,
- 38599, conf, Murex, Borstad 34-10H-A 2MB, West Tioga,
- 38600, conf, Murex, Sheldon Mark 34-22H-A 2MB, Tioga,
- #38601, conf, Murex, Borstad 34-10H-1 1MB, West Tioga, no production data,
Patterson 280:
- November 30, 2021: --
- December 20, 2021: 38598, Murex, Sheldon Mark 34-22H-1-3MB -- first day;
- December 27, 2021: 38601, Murex, Borstad 34-10H-A 1MB
- December 30, 2022: 38600, Murex, Sheldon Mark 34-22H-A 2MB,
- January 18, 2022: 38600, Murex, Sheldon Mark 22-10H-A-2MB,
- February 28, 2022: 38599, Murex, Borstad 34-10H-A-2MB,
- March 25, 2022: 38601, Murex, Borstad 34-10H-A-1MB,
- --, 38598, Murex, Sheldon Mark 34-22H-A 3MB, Tioga