Thursday, October 7, 2021

In Case You Missed It -- KMI Proposes Short Pipeline In Williams County -- October 7, 2021

KMI: will lay a short pipeline in Williams County to connect to the DAPL. Link here. Direct to Amy R. Sisk here.

  • Hiland Crude, a subsidiary of KMI, is proposing a 2.9 mile pipeline in Williams County
  • origin: at its Epping Station (a few miles southwest of Williston)
  • terminus: unspecified tap-in location to the DAPL
  • 8-inch diameter, steel
  • will transport 30,000 bopd with capacity for double that (63,000 bopd)
  • $5.4 million
  • $5.4 million / 2.9 miles = $1.9 million / mile or rounding, $2 million / mile
  • remember when greenfield pipeline ran about $1 million / mile
  • this helps put value on existing pipelines across the nation
  • the burggraben widens


No comments:

Post a Comment