The well:
- 24745, 1,916, MRO, Melvain Fox USA, Moccasin Creek, first production, t2/15; cum 580K 1/21; fracked 12/26/14 - 1/2/15; 4.2 million gallons of water; 86.7% water by mass; from the file report:
- 50 stages; 5.258 million lbs proppant;
- target: Three Forks (NOS)
- spud: morning of August 7, 2014;
- surface hole rig skidded to next hole;
- vertical hole: begun September 2, 2014;
- curve landed at 10,552' TVD
- directional tools pulled and casing set: September 6
- lateral section:
- began: September 9, 2014
- TD: 24,828' MD, September 18, 2014
- background gas: unremarkable;
- well-bore 100% within the Three Forks formation, and 79% within the MOC geology defined target interval;