- both the lower court and the appeals court agree that the easement was granted illegally in 2017;
- the appellate court is leaving the interim status of the pipeline's operations up to the Biden-led Army Corps
- President Biden has not weighed in on the DAPL
- his vice-president and his interior secretary nominee both support shutting down the pipeline
- next court hearing scheduled for February 10, 2021