- 36690, SI/NC, Petro Harvester, Three Forks, first bench; FTH1 27-34 161-92 B, Foothills, t--; cum 16K first full month of production;
Pool | Date | Days | BBLS Oil | Runs | BBLS Water | MCF Prod | MCF Sold | Vent/Flare |
---|---|---|---|---|---|---|---|---|
BAKKEN | 12-2019 | 31 | 16006 | 15705 | 102131 | 20477 | 0 | 20477 |
BAKKEN | 11-2019 | 10 | 539 | 0 | 22152 | 376 | 0 | 376 |
From the file report:
- 13 miles north of Powers Lake, Burke County; sits on a pad with intentions of drilling a lateral through the Three Forks, first bench;
- Patterson 348, a modern top drive rig with walking capabilities; surface to TD in 13 days;
- vertical to KOP: 48.9 hours
- KOP to curve TD: 12.8 hours
- lateral with one assembly: 55.7 hours
- total lateral footage: 9,906'
- target window: 12- 20' into the Three Forks first bench;
- exposed 75.6% of the lateral borehole to the target window;