Sunday, June 2, 2019

Random Look At CLR Wells In Brooklyn Field That Have Been Recently Fracked -- June 2, 2019

April 7, 2022: updating two newer pads sited in this section, section 17-155-98:

  • 38363, conf, CLR, Springfield FIU 7-8H,
  • 38362, conf, CLR, Springfield FIU 8-8H1
  • 38361, conf, CLR, Springfield FIU 9-8H, 
  • 38360, conf, CLR, Springfield FIU 10-8H1,

 

  • 38299, drl, CLR, Rolf Federal 7-17H, Brooklyn,
  • 38298, drl, CLR, Rolf Federal 8-17H1, Brooklyn,
  • 38297, drl, CLR, Rolf Federal 9-17H, Brooklyn,
  • 38296, drl, CLR, Rolf Federal 10-17H1, Brooklyn,
  • 38295, drl, CLR, Rolf Federal 11-17HSL, Brooklyn,
  • 38294, PNC, CLR, Gjorven Federal 8-16HSL1, Brooklyn,
  • 38293, drl, CLR, Springfield 11-8HSL, Brooklyn,
  • 38292, PNC, CLR, Bismarck 8-9, Brooklyn,

Graphics updated:


The wells (as they come off the confidential list):

  • 34695, 1,601, CLR, Rolf 6-17H1, Brooklyn, t4/19; cum 198K 7/20; offline 4/20; back on line 7/20;  cum 238K 5/21;
  • 34696, 1,324, CLR, Rolf 5-17H1, Brooklyn, t4/19; cum 128K 7/20; offline 4/20; back on line 7/20; cum 159K 5/21;
  • 34697, 1,760, CLR, Rolf 4-17H, Brooklyn, t4/19; cum 187K 7/20; offline 4/20; back on line 7/20; cum 227K 5/21;
  • 34698, 1,872, CLR, Rolf 3-17H1, 58 stages; 8.1 million lbs; Brooklyn, t4/19; cum 161K 7/20; offline 4/20; back on line 7/20; cum 186K 5/21;
Original Post
Look at these posts for background:
  • 20183, 282, CLR, Rolf 1-20H, API: 33-105-02100, s6/11; t6/11; cum 403K 7/20; FracFocus, no re-frack; NDIC, no sundry re-frack form; off line 5/20; back on line 7/20; cum 428K 5/21; this well is tracked here; huge jump in production;
  • 21086, 667, CLR, Springfield 1-8H;  t1/12; cum 303K 7/20; FracFocus: no re-frack data; no NDIC data showing re-frack; off line 5/20; back on line 7/20; tracked here; huge jump in production;
The graphic:



The wells, FracFocus data: gallons of water used; percent of total stim that was water:
  • 34768, 1,395, Helena - HSL1, API: 33-105-04751, 9.436 million gallons; 90.2% water; t3/19; cum 148K 7/20; off line 4/20; back on line 7/20;
  • 34694, 2,006, Springfield - HSL, API: 33-105-04731, 10.566 million gallons; 89.0% water; t2/19; cum 159K 7/20; off line 4/20; back on line 7/20;
  • 34693, 1,376, Springfield - H1, API: 33-105-04730,  9.610 million gallons; 90.2% water; t3/19; cum 131K 4/20; offline 4/20; remains off line 7/20;
  • 34692, 1,553, Springfield- H, API: 33-105-04729, 10.582 million gallons; 88.9% water; t3/19; cum 150K 7/20; off line 4/20; returns to production, 7/20;
  • 34691, 940, Springfield - H1, API: 33-105-04728,  9.274 million gallons; 89.8% water; t4/19; cum 133K 7/20; off line 4/20; returned to production, 7/20;
  • 34690, 1,058, Springfield - H1, API: 33-105-04727,8.596 million gallons; 90.3% water; t4/19; cum 122K 4/20; remains off line, 7/20;

See production data above for these wells;
  • 34698, Rolf - H1, API: 33-105-04735, 9.383 million gallons; 89.4% water;
  • 34697, Rolf - H, API: 33-105-04734, 9.518 million gallons; 87.9% water;
  • 34696, Rolf - H1, API: 33-105-04733, 9.215 million gallons; 87.7% water;
  • 34695, Rolf - H1, API: 33-105-04732, 9.704 million gallons; 88.3% water;

The wells fracked above "essentially" refracked these two wells.
  • 20183, Rolf, see above;
  • 21086, Springfield, see above;

2 comments:

  1. Hi Mr. Oksol, I frequently visit this site to get my Bakken fix. Thanks. Don't know if this is the best way to ask, but do you have an idea when the new Rolf wells might come on line?

    ReplyDelete
    Replies
    1. I could be way wrong on this but a quick look and I often misread things.

      But I see that CLR had the Patterson 901 rig on that pad in December, 2021, and January, 2022. In the most recent look, April 5, 2022 (https://themilliondollarway.blogspot.com/2022/04/active-rigs-as-reported-by-ndic-april-5.html) the rig is off that pad suggesting all wells have been drilled to depth.

      The long pole in the tent is getting the frack teams. Purely guessing, the wells will be on line not sooner than three months from now (July, 2022) and not later than 9 months from now (December, 2022). Purely guessing and the operators are constrained by getting frack spreads to complete the wells.