- I can't remember where I blogged it and I can't remember what I said was optimal number of rigs/frack team ratio, but I believe I said it was in the 4/1 neighborhood -- every four active rigs require one dedicated frack team
- KOG: 6 rigs now; ramping to 7 rigs; one dedicated HAL frack team as of 1Q12
- OAS: 9 rigs now; ramping to 12 rigs; three dedicated frack teams and Oasis Well Services should begin operations this quarter (1Q12)
All things being equal, getting your well fracked/completed as soon after the well reaches total depth may be one of the most important things a company can do. (Lousy grammar, I know, but you get the point.)