Monday, October 3, 2016

Update On Wind Farm Projects In Western North Dakota -- October 3, 2016

On my trip back to North Dakota last weekend, I saw wind turbines being transported south to Hebron, North Dakota, and saw towers being raised at the Lindahl Wind Project north of Tioga.

Towers, nacelles, and blades are all being staged out of Red River Oilfield Services east of Williston.

For the Tioga project, the components are being brought from Red River (Williston) to the Pinnacle Truck Stop south of Tioga, staged there, until the cranes are ready for them.

Data points, quickly and briefly.

Sunflower Wind Project
  • south of Hebron, ND
  • up to 55 wind turbines in Morton County
  • 25 wind turbines in Stark County
  • Vestas or GE
  • approved July 8, 2014
  • $180 million project
  • 110 MW
  • $1.6 million / MW
  • Basin Electric will purchase 
  • components from China
Lindahl Wind Project
Two videos of staging area at Red River Oilfield Services, east of Williston:


Wind_Rich_1_Sept_2016



Wind_Rich_2_Sept_2016


Turn down / off the volume of the videos below.

Two videos of staging area at Pinnacle Truck Stop south of Tioga, ND:

Pinnacle_Blades


WInd_Pinnacle_Staging

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.