Sunday, February 8, 2015

Random Update On Slawson's Matilda Bay In Stockyard Creek (#27635) -- February 8, 2015

Original observation:

September 12, 2014: a failed frack; will it be re-fracked?
  • 27635, 137, Slawson, Matilda Bay 1-15H, Stockyard Creek, 8 stages; planned for 24, mechanical problems; 600,000 pounds proppant; single section spacing, t6/14; cum 13K 12/14; went off-line middle of July, 2014; then began producing again 10/14;
Upates

February 8, 2015: no frack data or updated sundry forms posted at the NDIC web site, but note the production profile:

PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN12-201431456046042756348833330
BAKKEN11-20143055846079538244908133527
BAKKEN10-20148173213945781145201412
BAKKEN9-20140000000
BAKKEN8-2014150035500
BAKKEN7-2014154203037500
BAKKEN6-201410124189525385000
 

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.