Data points:
- ONEOK announces "open season" for previously announced Bakken Crude Express Pipeline
- 1,300 mile crud oil pipeline
- from Williston Basin to Cushing hub
- 200,000 bopd
- construction to begin in early 2014; completion by mid-2015
*******************
Data points (some numbers rounded)
- Alliance Pipeline gets FERC approval
- 80-mile pipeline from Tioga, ND; ties in with Alliance mainline in ND --> Chicago
- natural gas; certified for 100 million cfd; underpinned with Hess contract for 60 million cfd
- pipeline is expandable; should be complete by summer, 2013
- Alliance Pipeline system in operation since 2000; 2,300 mile integrated Canadian and US high-pressure gas transmission pipeline system
- from Western Canadian Sedimentary Basin and Williston Basin to Chicago
- delivers an average of 1.6 billion cfd
********************
Data points:
- Ineos Europe AG, Switzerland, will ship ethane from Marcellus to Europe
- through Sunoco-operated Mariner East pipeline
- still requires FERC approval of the Mariner East pipeline