Keystone Pipeline Shutdown Update -- I'm Shocked! Shocked! -- July 22, 2022

 From argusmedia two days ago:

Companies Taking Advantage Of America's LNG Boom -- Oilprice -- July 22, 2022

Link to Alex Kimani.

Lots of data.

Matterhorn Express Pipeline:

  • from Waha, TX, to Katy, near Houston, TX
  • 2.5 billion cubic feet per day of natural gas
  • 490 miles; 42-inch pipeline (huge diameter -- almost four feet, think about that)
  • in service date: 2H24
  • consortium has reached FID: WhiteWater Midstream, LLC; EnLink Midstream, Devon Energy Corp, MPLX LP
  • another link: Matterhorn Express Pipeline

The Map Page -- July 22, 2022

Earlier this morning I told a reader it was a straight shot, six hours from Nuevo Laredo, Mexico, to Austin, Texas.  I was wrong. It's four hours.

Neuvo Laredo: state of Tamaulipas. Etymology unknown. 

Two links:

Nuevo Leon is a weirdly shaped state that managed to have its border drawn in a way that gave it just a little 9-mile border with the United States and more specifically the state of Texas.

In the US, we gerrymander voting districts.

In Mexico, they gerrymander entire states.

Elon Musk: brilliant. Attention to detail.


 

One more reason Tesla moved to Texas.

Also, steady stream of new landscapers to mow the lawns around his new facilities.

Week 29: July 17, 2022 -- July 23, 2022.

Top story of the week:

  • Joe Biden is still president.
    • tests positive for Covid-19; has the sniffles; will work from "the residence" indefinitely
      • says he also has cancer
    • Kamala Harris: identified as close contact
    • Nancy Pelosi: third in line

Top international non-energy story:

  • The Ukraine war drags on.

Top international energy story:

  •  Situation continues to worsen in Europe
  • Critical Russian turbine for Nord Stream 1 held up in Germany after being "returned" from Canada

Top national non-energy story:

Top national energy story:

  • WTI drops below $90; continuing its two-week slump
  • US EPA threatens to shut down the Permian over emissions

Top North Dakota non-energy story:

Top North Dakota energy story:

  • NDIC website appears to be nearly completely fixed; GIS map server up and running

Geoff Simon's top North Dakota energy stories:

Bakken economy:

Commentary:

Five Wells Coming Off Confidential List Over The Weekend -- July 22, 2022

Schlumberger: profit more than doubles. Links everywhere.

  • net income: $959 million
  • EPS: 67 cents
  • a year earlier: $431 million and 30 cents/share
  • ups guidance

Switzerland: to release oil from its SPR

  • refined products from Germany not reaching Switzerland due to Rhine low water level

Germany: trying to save itself; bails out Uniper at a cost of €15 billion; peanuts.

  • government took 30% stake in Uniper
  • credit line to Uniper upped to €9 billion (previously €2 billion)

Fed: I'm old enough to remember when the Fed was purposely trying to spur inflation.

They succeeded. 

Nancy Pelosi: third in line. 

*****************************
Back to the Bakken

Far Side: link here.

WTI: $95.50 but had been lower overnight.

Natural gas: $7.959 --- that's about as close to an 8-handle as one can get. Think ISO-NE, ISO-NY.

Active rigs: 45 or thereabouts

Sunday, July 24, 2022: 23 for the month, 23 for the quarter, 362 for the year

  • 38675, conf,  CLR, Bang 6-4H,
  • 37498, conf, Petro-Hunt, State 159-94-25A-36-1HS,

Saturday, July 23, 2022: 21 for the month, 21 for the quarter, 360 for the year

  • 32113, conf, Slawson, Armada Federal 1 SLH,

Friday, July 22, 2022: 20 for the month, 20 for the quarter, 359 for the year

  • 38665, conf, Slawson, Armada Federal 8-14-13H,
  • 32112, conf, Slawson, Armada Federal 9-14-13TFH, 

RBN Energy: court decision helps supply access to LNG export facilities.

Europe is trying to wean itself off Russian natural gas, and few things would help it more than an expansion of U.S. LNG export capacity. But LNG projects don't just need long-term commitments for their output, they also need pipelines to transport natural gas from the Marcellus/Utica and other distant production areas to their coastal liquefaction plants. And, in case you hadn't noticed, new interstate gas pipelines face a lot of hurdles during the regulatory review process these days — getting a pipeline approved is tougher than snagging a Saturday morning tee time. Which brings us to, of all things, an important court ruling. In today's RBN blog, we discuss the implications of the DC Circuit's decision in City of Oberlin v. FERC. 

On July 8, the U.S. Court of Appeals for the District of Columbia Circuit (a.k.a. the DC Circuit) updated a decision that could have a significant impact on the supply of feedgas to LNG export facilities. In the case of City of Oberlin, Ohio v. FERC, the DC Circuit reversed an earlier finding that the Federal Energy Regulatory Commission (FERC) had not explained why export volumes on a proposed interstate pipeline project can be used to help justify approval of the new pipe projects. The case involved the city of Oberlin's challenge to FERC's approval of the NEXUS pipeline, carrying natural gas from the Utica Shale in eastern Ohio to the gas hub in Dawn, ON (among other destinations). The project sponsors had included the gas flows to Dawn as support for approval of the pipeline, to help meet the requirements of FERC’s “certificate policy” that a public benefit had to be shown for pipeline construction to be authorized.

In what the DC Circuit now refers to as its "Oberlin I" decision, the court, in 2019, found that FERC needed to explain why volumes on NEXUS going to Canada were a benefit to the U.S. public. That decision had been used by LNG opponents, such as Sierra Club, to claim that the same issue affects feedgas pipelines built to serve LNG export terminals. They argued that such pipelines shouldn’t receive certificates to allow construction or the eminent domain rights that automatically go with those certificates if they didn’t show a benefit to the U.S. public. The DC Circuit's decision last month (“Oberlin II”) reversed Oberlin I, finding that FERC has now explained itself well enough and that, yes, natural gas exports can provide public benefits in the U.S. So, does this reversal clear the way for LNG feedgas pipelines to be built without running into legal roadblocks? Well, it pretty much knocks down one potential roadblock, but that’s a start.