Updates
November 16 2014: see first comment, reply.
November 16, 2014: a reader provides this update --
Current drilling rigs list shows a rig on location since October 9, 2014, for this Tyler well:
since 10-09-14.
- 29280, conf, MBI, Bahley 31-1,
This is the second of two permitted, the other being the Wolberg 18-1--located at--08-136-99, in the Rocky Ridge field.
On that location (Wolberg) they moved in, drilled, plugged, and moved out in about one week.
Oilfield friend told me MBI was after Tyler cores, didn't expect to be completing either of the wells. Could be it's a smaller drilling rig and is waiting for a location somewhere else or could be MBI ran into something better than expected.October 7, 2014: a reader drove past #29279 --
They were drilling north of the Rundel Well 1 mile north and 1/2 mile west. They were finished today: all rigged down and the 8 oil tanks are already on the location ready to be set up.
Original Post
Testing the Tyler? A reader says the recent permits by MBI will be testing the Tyler, but does not expect to produce from some/all of these wells:
- 29279, conf, MBI, Wolberg 18-1, Rocky Ridge, almost midline on a diagonal from Bowman to Dickinson,
- 29031, conf, MBI, Hueske 30-1, wildcat, a rig is on site as of September, 2014, 30-142-92, about 25 miles northeast of Dickinson;
- 29280, conf, MBI, Bahley 31-1, wildcat, about 20 miles southwest of Dickinson, just north of the Wolberg