A 61-mile transmission line between Williston and Tioga has been completed and gone operational this week.By the numbers:
Work on the 230-kilovolt line began on May 10. The line runs from a substation owned by the Western Area Power Administration to another substation owned by Mon-Dak Utilities near Tioga.
- Total cost: $26.5 million
- $15 million financed by North Dakota Transmission Authority
- 406 single-pole towers, no guy wires (important issue in snow mobile country)
- Seven towers per mile, on average