I'm starting to lose the bubble(s) on all of the pipeline projects. At the linked story, there are a number of Enbridge projects.
Some data points from the article:
Lakehead System (Enbridge): increasing capacity on:
- Alberta Clipper pipeline (Line 67), into Superior, WI; from 450K bopd to 570 bopd
- Southern Access pipeline (Line 61) from Superior, WI, to Flanagan, near Pontiac, ILL; from 400K bopd to 560K bop
- only additional pumping power needed; no new pipeline construction
- in service by mid-2014; $360 million
- Spearhead North pipeline (Line 62) between Flanagan and Griffith, IN; from 130K bopd to 235 bopd
- will also add a 330K bbl tank at Griffith to existing storage
- will replace additional sections of ENB Line 6B previously announced which will increase capacity from 240K bopd to 500K bopd
- Line 6B expansions and previously announced Line 5 50K bopd expansion by 2014; $2.2 billion
- construct a 35-mile pipeline adjacent to ENB Toledo Pipeline (Line 17), originating at Line 6B in Michigan and serving refineries in MI and OH
- a reversal of Line 9B from Westover, Ontario, to Montreal
- more power, not more pipeline