Monday, February 1, 2021

Closer Look At Another Incredible Hess Labar Well -- Look How Fast They Drilled This Well -- February 1, 2021

The well:

  • 37066, conf-->loc/A, Hess, EN-Labar-154-94-1003H-9, 33-061-04618, Alkali Creek, first production, 8/20; t--; cum 143K 12/20; fracked 5/28/20 - 6/5/20: 6.5 million gallons of water; 83.8% water by mass;
PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN12-20203119633197569187000
BAKKEN11-2020302557225487910138279369681311
BAKKEN10-2020312637426456104374203141469562
BAKKEN9-20203030026300171193247067446852382
BAKKEN8-202024415854138436422541273412819999

Look at this from the file report:

  • spud date: March 1, 2020; serious drilling did not begin until 8:00 a.m., March 3, 2020
  • cease drilling: March 8, 2020
  • target: middle Bakken
  • reached KOP: 10:15 p.m. March 3, 2020 -- 14 hours to drill the vertical
  • KOP:
    • build began at 9:00 a.m., March 4, 2020
    • landed in the middle Bakken; and completed the curve at 5:30 p.m. CT, March 4, 2020; same day
  • lateral:
    • began at 4:15 a.m., March 6 -- so there was no drilling for a full day (March 5 -- no drilling)
    • the center of the ideal geological target area: 30' vertical depth inside the middle Bakken formation;
    • overall drilling window had a thickness of 20' with the top of the target window located 20 vertical feet inside the middle Bakken and the base ending at 40' total vertical feet;
    • the entire lateral drilled within the target geological area except 270' that was drilled within one foot of the base target location
    • as noted, drilled ceased on March 8, 8:10 p.m. CT -- two and a half days to drill the lateral;
  • max gas appeared to be 4,024 units;
  • TVD: 10,515.86'
  • MD: 21,070'

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.