The well:
- 27591, 2,079, Enerplus, Monarch 152-94-32D-29H, Antelope, a huge well,
44 stages; 8.9 million lbs; about 200,000 lbs/stage; NGL unit to reduce
flaring on-site; large volume deethanizer (stabilizer) on site; spud
Feb 28, 2014; big rig moved on sit May 19, 2014; began lateral on May
29, 2014; TD June 12, 2014; total days, 29; total drilling hours 336 (14
days); TVD, 10,614 feet; lateral, 8,815 feet; trip gases as high as
3,400; t12/14; cum 513K 12/14;