Sunday, June 30, 2019

MRO's Bill Connolly In Bailey Oil Field -- Re-Fracked; New Production 40X Greater After Re-Frack -- June 30, 2019

Updates

August 8, 2019: updated recent production:
PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN6-20193022893228083117620766140154676
BAKKEN5-20193124374245254640319440102486967
BAKKEN4-20192629475295359024520752534412964
BAKKEN3-201954502375520278000


Original Post

For newbies: MRO has an aggressive re-frack program in the Bailey oil field. Here is another example.

The well:
  • 16736, 377, MRO, Bill Connolly 21-25H, Bailey, t1/108; cum 262K 4/19;
Previous post:
May 13, 2019: #16736, huge jump in production but only 5 days of production; in area of a lot of new fracking; need to check up on production over three or four full months. Re-fracked, 2/22/19 - 3/9/19; 6 million gallons of water; 90% water in the injection;
PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN4-20192629475295359024520752534412964
BAKKEN3-20195450237552027831545572030
BAKKEN2-20190000000
BAKKEN1-20190000000
BAKKEN12-20180000000
BAKKEN11-201812344031969
BAKKEN10-201831844680243786420128
BAKKEN9-20183081791014376647858
BAKKEN8-201831837110313879753029

So, note that the 26-day production of 29,475 bbls extrapolates to 34,010 bbls/30-day month.

How did this well do at the original frack?

BAKKEN10-20083145884378985249724970
BAKKEN9-200830472248801003238523850
BAKKEN8-200831523951731185283928390
BAKKEN7-200823272426811477126512650
BAKKEN6-20083030282898699134413440
BAKKEN5-20083133113457725152115210
BAKKEN4-20083037323639844185818580
BAKKEN3-200831475346561045197719770
BAKKEN2-200829574658111239213221320
BAKKEN1-2008268262792221433133130

So, for the cost of mediocre re-frack, MRO got a huge "new" well. 