August 13, 2021: cleanup update. Unremarkable.
August 9, 2021: the fires are all out at the pad.
August 3, 2021, 1:06 a.m.: update; it's still burning.
Original Post
See this post for background to this story.
For full production profile for the four wells mentioned in this post, see this post.
Still on fire at end of week. Started a week ago, Thursday. Goal to have it "under control" by end of this week.
Lynn Helms, director of the Department of Mineral Resources, briefed members of the state Industrial Commission on the fire at a meeting on Tuesday. He said three wells are on fire, and a fourth has been shut down to prevent it from catching fire as well.
I tried figuring out what pad this was some days ago, but was unable. Now we have another hint: a four-well pad, north of Charlson and "just south" of the lake.
Going north of Charlson to the lake, there is only one four-well pad.
Okay, I haven't found any article that tells me which pad is involved. So, I will try again. I may be way off again, and if readers convince me I'm wrong, I will remove this post or at least that part of it that is clearly wrong.
So, here goes. Again, this is just conjecture.
Graphics below:
- first map: the four wells, zoomed in; one will see only four wells, but five directional/horizontal legs in this graphic;
- second map: the four wells, but note that one of the directional/horizontal legs was quite short (identified with a question mark), and the "second" horizontal from this well eventually went due south and ran parallel to the other three horizontal wells. In fact this well had two long laterals; after the short lateral abandoned, the long sidetrack #1 almost made it to planned depth, but problems again, for a second sidetrack (so this well has a lateral and two sidetracks).
- third map: from google maps; the location of Charlson, ND, and the location of the only four-well pad north of Charlson.
First map:
Second map:
Third map:
For full production profile for the four wells mentioned in this post, see this post.
The wells:
- 34655, 1,748, Petro-Hunt, USA 153-95-3B-10-1H, Charlson, F, t8/19; cum 555K 5/21; middle Bakken; F, cum 567K 6/21;
- 34656, 1,131, Petro-Hunt, USA 153-95-3B-10-2H, Charlson, F, t8/19; cum 266K 5/21; Three Forks; AL, cum 276K 6/21;
- 34657, 1,328, Petro-Hunt, USA 153-95-3B-10-3H, Charlson, F, t8/19; cum 587K 5/21; middle Bakken; F, cum 618K 6/21;
- 34658, 1,050, Petro-Hunt, USA 153-95-3A-10-4H, Charlson, F, t8/19; cum 279K 5/21; Three Forks; F, cum 288K 6/21;