Because the NDIC has still not "fixed" their IT problems --which have been going on since July 14, 2021 -- I might have to follow some things differently, at least in a different format. 

That's the reason for this post.

Updates

  • reports first production: 7/21 -- 458 bbls; still confidential so we don't know number of days;
  • active rigs, May 5, 2021: Petro-Hunt: Zabolotny
  • off confidential, September 30, 2019: #35628
  • off confidential, August 25, 2021: #35629
  • two new permits, October 24, 2018 -- a two-well Zabolotny pad in lot 4 section 3-144-98;
  • a DUC reported as complete, April 24, 2013: #15046
  • off confidential, July 26, 2012: #21534; permitted in 2011;

The wells :

  • 37987, a new permit, November 20, 2020, Petro-Hunt, Zabolotny 144-98-4A-9-1H, Little Knife,
  • 35629, 755, Petro-Hunt, Zabolotny 144-98-3B-10-3H, Little Knife, t7/19; cum 7K over 11 days; cum 145K 8/21; not taken off line;
  • 35628, 649, Petro-Hunt, Zabolotny 144-98-3B-10-2H, Little Knife, t7/19; cum 38K 8/19; cum 131K 8/21; not taken off line;
  • 21534, 783, Petro-Hunt, Zabolotny 144-98-3A-10-1H, Little Knife, t5/12; cum 781 bbls 5/12; cum 202K 8/21; was off line 4/21 - 7/21; back on line 8/21; no halo effect;
  • 15934, PA/82, Petro-Hunt, Zabolotny 4D-4-2H, Little Knife, t5/06; cum 13K 3/14;
  • 15046, 11, Petro-Hunt/Flying J Oil & Gas, Zabolotny 8-4, a Duperow well, Little Knife, this was a Red River well that produced 65K, completed back in 2001; now it's a Duperow well; cum 18K 8/21;
  • 6225, 1,392, Petro-Hunt/Gulf Oil, Zabolotny 2-3-3-C, Little Knife field, Madison Pool, t12/77; cum 3.0321 million bbls 6/17 and still producing 1,000 bbls/month; 6/17; on the monster well list; see this post; cum 3.078941 million bbls; still producing 1,000 bbls/month;