Pages

Thursday, April 14, 2022

ISO New England -- Maine -- Why Maine Has Failed To Meet Its Ambitious Wind Power Goals --April 14, 2022

Link here, from a reader, thank you.

  • NE ISO: demand generally 12,000 to 16,000 MW
  • note article:
    • goal: 3,000 MW capacity
    • actual: 1,000 MW capacity
    • nameplate capacity: 1,000 MW
    • actual: 250 MW
    • 250 / 16,000 =  1.6%
    • in line with projections and data provided by EIA
  • largest wind farm in the state: Bingham Wind Farm
    • 56 turbines
    • 186 MWs: nameplate capacity
    • actual: 46 MWs; about a MW per turbine

********************************
On Their Way To State

Grapevine's Lady Mustangs Soccer Team on their way to Texas state semi-finals championship game Thursday.

Finals on Saturday,


High school booster club send-off:

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.