Pages

Saturday, April 3, 2021

Update On Natural Gas Pipelines Along North Dakota / Minnesota State Line -- April 3, 2021

Available at The Grand Forks Herald but you will hit a paywall. The story is here without a paywall.

After a three-month winter break, work on the $8.5 million Dakota Natural Gas pipeline project in Traill County, N.D., ramped up again in March.

The project, which unanimously was approved by the North Dakota Public Service Commission in September, will connect to the Viking Gas Transmission line in western Minnesota and deliver natural gas to commercial and residential customers in the Traill County, in cities of Hillsboro and Mayville and to rural customers along the route.

The 63-mile pipeline will be made of steel, except in Hillsboro and Mayville, where it will be high-density plastic.

About 750 commercial and residential customers in Traill County will be able to access the pipeline if they choose to do so.

Last year, Dakota Natural Gas finished a $4 million pipeline project in Drayton, N.D., where customers included American Crystal Sugar Co.

Meanwhile, representatives of Dakota Natural Gas also are studying the possibility of installing natural gas pipelines to the Traill County cities of Portland and Hatton.

Nearly all of the pipeline on the North Dakota side of the Traill County project has been laid, and work soon will begin on the Minnesota side.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.