Rigs Don't Matter -- Not To Be Taken Out Of Context -- April 30, 2021

Link here. This article is archived.

Natural gas processing plants in North Dakota are tracked here.


From the linked article:
Although oil production in most US shale basins is not expected to reach pre-coronavirus levels until at least late 2023, additional processing and higher gas-to-oil ratios might still lead to natural gas growth in the oil-rich Bakken.

Oneok increased its first-quarter natural gas and natural gas liquids volumes processed in the Williston Basin and plans to bring another 200 MMcf/d of processing capacity online before year-end, which will further reduce flaring in North Dakota.

Gas volumes processed in the Rocky Mountain region increased 5% while NGL raw feed throughput volumes grew 20%, the company reported in its first-quarter 2021 earnings call on April 28. This occurred despite winter storm production freeze-offs in February and lower year-over-year drilling activity in the region.

"The Williston Basin continues to surpass our expectations," Oneok CEO Terry Spencer said. "Our increased operations were not reliant on increased rig activity or commodity prices. Instead, it is based on DUC inventory, rising gas to oil ratios and increased ethane demand."

Oneok chief operations officer Kevin Burdick said: "There are 350 DUC wells on our dedicated acreage. With eight completion crews, there is no need for additional drilling or completion crews to maintain our volumes throughout the year. Any additional activity would provide upside."

With more than 200 MMcf/d of natural gas still being flared in the Bakken, according to the latest data by the North Dakota Industrial Commission, more volumes of gas can still be captured even if production stagnates for the foreseeable future, especially with wells demonstrating higher gas-to-oil ratios.

The company is moving forward with its 200 MMcf/d Bear Creek natural gas processing plant expansion and related infrastructure in the Williston Basin, which is slated for completion in the fourth quarter of 2021.