Pages

Wednesday, February 26, 2020

A Closer Look At The CLR Imsland First Bench Well -- February 26, 2020

The well:
  • 35830, 509, CLR, Imsland 5-31H1, Hamlet, t9/19; cum 51K 12/19; 34 stages; 6 million lbs;
From the file report:
  • Divide County
  • objective: steer the well within the 12' target zone located 13' below the Three Forks top
  • rig: H&P 640
  • drilling
    • 5-26/19: skid rig onto Imsland 5-31H1
    • 5-27/19, 06:36: start drilling vertical hole
    • 5-29/19, 5:40: reach KOP, 8,910';
    • 5/29/19, 21:57: start building curve
    • 5/30/19, 10:13: land curve
    • 6/11/19, 8:27: start drilling lateral
    • 6/14/9, 7:44: reach total depth of 19,956'
  • drilled 86.7% within the 12-foot target zone
  • background gases averaged 417 units throughout the lateral
  • planning/prognosis, TVD:
    • upper Bakken shale: 9,206
    • middle Bakken shale: 9,216
    • lower Bakken shale: 9,281
    • Three Forks: 9,310
    • first bench target: 9,330
    • end of lateral: 9,210 (no typo)
Production:
PoolDateDaysBBLS OilRunsBBLS WaterMCF ProdMCF SoldVent/Flare
BAKKEN12-20193116146162213072619121187160
BAKKEN11-20192913637137483286114579142140
BAKKEN10-201931147821484340858169561655512
BAKKEN9-20191859975352268205978595622
BAKKEN8-201933302986000

Note: "no" flaring. 

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.