Through August 26, 2019.

Disclaimer: this is dynamic data. The status of the wells can change daily. There will be factual and typographical errors, but not many. I make simple arithmetic errors.

Calendar days in 2019 so far: 238 days.

Number of permits issued (as of yesterday, August 26, 2019): 1,012

Projected number of permits for calendar year 2019: 1,552 permits

Permit numbers: #35899 - #36910, inclusive

Status of wells:
  • SI/NC (DUCs): 60
  • PNC: 7
  • PA (dry): 1
  • LOC: 346
  • DRL: 150
  • CONF/PRODUCING: 4
  • CONF: 439
  • IPs reported: 5
As a percent of total permits:
  • Drilled to depth, reported: 65 / 1,012 = 6%: 
  • CONF: 43%
  • LOC: 34%
  • SI/NC (DUCs): 6%
  • DRL: 15%
Confidential but producing:
January 22, 2019
35985
C-P
Nine Point Energy
Little Muddy 6H
WMS
Williston
January 22, 2019
35986
C-P
Nine Point Energy
Little Muddy 7H
WMS
Williston
January 22, 2019
35987
C-P
Nine Point Energy
Little Muddy 8H
WMS
Williston
February 14, 2019
36089
C-P
WPX
Ruby 31-30HEL
MCK
Antelope


IPs reported (third column is the IP; second column is the file number):
February 26, 2019
36127
3537
Bruin
Borrud 156-101-1B-12-3H
WIL
Tyrone
January 9, 2019
35939
2239
Whiting
Nelsen 11-2HU
MCK
Elk
January 16, 2019
35960
1796
Newfield
Goliath 150-98-5-8-8HLWR
MCK
Siverston
February 5, 2019
36044
1683
Kraken
Ruffing 27-34 5H
WMS
Lone Tree Lake
February 5, 2019
36045
1302
Kraken
Ruffing 27-34 4H
WMS
Lone Tree Lake


Selected operators with number of permits:
  • XTO: 110
  • WPX: 46
  • Whiting: 118
  • Slawson: 41
  • Rimrock: 61
  • Oasis: 15
  • Newfield: 25
  • MRO: 54
  • Lime Rock: 15
  • Kraken: 36
  • Hess: 119
  • Equinor: 27
  • EOG: 11
  • Enerplus: 45
  • CLR: 109
  • Bruin: 29
  • BR: 79
By county:
  • Dunn: 252
  • McKenzie: 302
  • Mountrail: 206
  • Williams: 231