- first phase to be complete in October
- second phase to begin next season
- federal funding: $10 million discretionary funds annually and $2 million in entitlement funding annually
- city agreed to $11 million
- airport had $6 million in reserves
- since then, bid amounts for the now $49 million second phase have decreased by $4 million; federa funding has increased by $6 million in extra discretionary funds
- bottom line: about $10 million "to the good"
- next phase: about $15 million
- total project cost: $65 million
Pages
▼
Saturday, September 23, 2017
Update On New Runway At Bismarck Airport -- September 23, 2017
From The Bismarck Tribune, data points: