Pages

Monday, October 22, 2012

Pipeline Updates of Interest, Selected

Link to Oil & Gas Journal here, re: ONEOK, update:

Data points:
  • ONEOK announces "open season" for previously announced Bakken Crude Express Pipeline
  • 1,300 mile crud oil pipeline
  • from Williston Basin to Cushing hub
  • 200,000 bopd
  • construction to begin in early 2014; completion by mid-2015
*******************
Link to Oil & Gas Journal, re: Alliance natural gas pipeline, North Dakota:

Data points (some numbers rounded)
  • Alliance Pipeline gets FERC approval
  • 80-mile pipeline from Tioga, ND; ties in with Alliance mainline in ND --> Chicago
  • natural gas; certified for 100 million cfd; underpinned with Hess contract for 60 million cfd
  • pipeline is expandable; should be complete by summer, 2013
  • Alliance Pipeline system in operation since 2000; 2,300 mile integrated Canadian and US high-pressure gas transmission pipeline system
  • from Western Canadian Sedimentary Basin and Williston Basin to Chicago
  • delivers an average of 1.6 billion cfd
********************
Link to Oil & Gas Journal re: Marcellus ethane to Europe, a first, much more to the story than the few data points below:

Data points:
  • Ineos Europe AG, Switzerland, will ship ethane from Marcellus to Europe
  • through Sunoco-operated Mariner East pipeline
  • still requires FERC approval of the Mariner East pipeline

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.